New schedule for London Games
LONDON
London Olympic organizers revised their construction timetable for the 2012 games, with some big changes to the plans outlined in their bid book.
The swimming venue, which was to be completed by December 2008, will now be finished in mid-2011 after the original design was deemed too expensive and extravagant.
The completion date of the velodrome has been moved from December 2008 to summer 2011, also because of revised plans.
The 80,000-seat main Olympic stadium is set to be finished in June 2011, four months later than originally planned.
London issued its original timetable in 2004 when it was bidding for the Games and was selected as host last year.
“Changes have been made to the 2004 outline timetable for some venues to ensure the most efficient use of resources,” London 2012 organizers said in a statement. “They will be completed in time for test events at least one year from the Games, but not so early that they sit vacant for extended periods prior to 2012 incurring maintenance costs.”
David Higgins, chief executive of the Olympic Delivery Authority, said the new timetable was “challenging but achievable.
“I recognize it is a bold move setting out indicative target dates that we can be measured against, but it is important that we are transparent and accountable.
“Some dates have moved. This reflects our ongoing detailed planning and project management.”
ASSOCIATED PRESS
| MOST POPULAR STORIES |
- Police probe death at York Street construction site
- Ontario’s apprentice ratio dispute continues to be split along union, non-union lines
- Hard Rock contracting companies fined over worker injuries
- Early LEED advocates were ‘pioneers,’ ACEC president says
- Two Ontario firms win Canadian Architect Awards of Excellence
- 20 Most Popular Stories
| CURRENT STORIES |
- EllisDon keeps moving up at the Ritz-Carlton
- Insulation association lobbies for inclusion of best practices in National Building Code
- AGC survey finds two-thirds of U.S. non-residential construction companies plan layoffs in 2009
- Bulldozer fatality halts work at Anatolia Minerals’ Copler gold project
- Canadian economy heads south for the winter
- Homicide charge laid in N.Y. crane collapse
- McKay-Cocker chooses Viewpoint software to integrate operations
- Great Lands digs deep at the Mona Lisa
- U.S. investors drop stakes in proposed TransCanada pipeline
- Aecon named one of Canada’s 10 Best Employers
- Solar module maker Day4 Energy lays off 95 workers
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Spotting the U.S. and Canadian Recoveries – Earliest Indicators (January 6, 2009)
- TYBA Projects (January 5, 2009)
- Ottawa’s Spending and Canada in Afghanistan (December 30, 2008)
Lifestyle Blog More 
- The Perils of Driving in the White Stuff (December 29, 2008)
- Economics Humour – Take my Dismal Science, Please (December 22, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Vanbots begins work on Thompson Rivers University’s House of Learning (Jan 6, 2009)
- City of Thompson plans new water treatment plant (Dec 30, 2008)
- Quadrangle Architects begins working drawings for new phase of Downtown Markham development (Dec 16, 2008)
- Designs for new Corrections Canada office set to begin (Dec 15, 2008)
- Haastown Holdings ready to accept subtrade pricing for Waterscape phase one (Dec 15, 2008)