LATEST NEWS
Sewer & Watermain
August 30, 2006
Construction
Cancelled project irks industry
City of Ottawa’s tender process in question
TORONTO
The cancellation by the City of Ottawa of a tender for reconstruction of part of King Edward Avenue has raised the ire of the local contracting community.
Low bidder R.W. Tomlinson Ltd. was notified in mid-August that the tender was being cancelled. The firm had submitted a $21.6 million bid.
“Unfortunately, the bids received for the work were considerably higher than the city’s budget for this project,” said purchasing officer Patty Arguin. “A decision was made to cancel the tender.”
The bid reportedly was $8 million above budget.
John DeVries
In a letter to Mayor Bob Chiarelli, Ottawa Construction Association president John DeVries said his organization believes this decision “and the underlying assumptions behind it are flawed and need to be revisited immediately as a result.
“This major reconstruction is a complex, multi-faceted project that resulted in two competitive bids, of $21.6 million and $23.4 million,” he said.
Phase 2 of the renewal project involves reconstruction from the MacDonald Cartier Bridge/Sussex Drive to St. Patrick Street.
Included is installation of a new watermain, sewer relining, preparation for burial of overhead utilities and completion of roadway reconstruction.
DeVries said “it is the association’s understanding that prime engineering consultant Delcan Corp. had provided the city with a budget estimate some $8 million below the low tender and had subsequently provided an opinion that the bids are overpriced.”
Delcan declined comment on the letter.
The company referred calls to city senior project manager Phill Kerridge. He could not be reached for comment.
“They are playing Monday morning quarterback now after receiving two competitive bids,” DeVries told Daily Commercial News.
Bert Hendriks, executive vice-president of Tomlinson’s municipal division, believes his firm submitted a “realistic” price given the complexities of the project, which he said involves digging five metres through solid rock.
“It’s crazy,” Hendriks said in an interview. “I thought we were pretty aggressive as it was. We beat the other guy by $2 million. Does that mean I have to beat somebody by $8 million to get the job.”
For its part, the association told the mayor that Tomlinson should be given the opportunity “to rebut possible erroneous assumptions and conclusions as to current construction market pricing.”
DeVries said city didn’t even sit down with the low bidder to negotiate changes, which would be in keeping with recommended procedures under the Canadian Construction Documents Committee document 23, a guide to calling bids and awarding construction contracts.
The association has not received a response to its letter.
But Hendricks said “the word on the street is that the matter is being re-evaluated.
“I heard that the consultants have taken another look at the budget and that they are now up to around $19 million or something.”
DeVries told the mayor that cancelling “this properly tendered project is unfair and has the potential to erode the excellent tendering relationship the city enjoys with the local construction industry.”
| MOST POPULAR STORIES |
- Police probe death at York Street construction site
- Ontario’s apprentice ratio dispute continues to be split along union, non-union lines
- Hard Rock contracting companies fined over worker injuries
- Early LEED advocates were ‘pioneers,’ ACEC president says
- Two Ontario firms win Canadian Architect Awards of Excellence
- 20 Most Popular Stories
| CURRENT STORIES |
- A New View of The Avenue
- RCCAO hosts industry-government roundtable on economic stimulus measures
- AGC survey finds two-thirds of U.S. non-residential construction companies plan layoffs in 2009
- Tucker Hi-Rise takes on X condominium project
- Canadian economy heads south for the winter
- Korky Koroluk: Biodiesel should be part of the fuel mix
- Canadian Centre for Policy Alternatives opposes tax cuts as form of stimulus
- Turkish construction industry hit hard by Russia’s economic slowdown
- Federal commission recommends 50 per cent gas-tax hike to finance U.S. road work
- Ground Zero construction official faces fraud charges
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Spotting the U.S. and Canadian Recoveries – Earliest Indicators (January 6, 2009)
- TYBA Projects (January 5, 2009)
- Ottawa’s Spending and Canada in Afghanistan (December 30, 2008)
Lifestyle Blog More 
- The Perils of Driving in the White Stuff (December 29, 2008)
- Economics Humour – Take my Dismal Science, Please (December 22, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Vanbots begins work on Thompson Rivers University’s House of Learning (Jan 6, 2009)
- City of Thompson plans new water treatment plant (Dec 30, 2008)
- Quadrangle Architects begins working drawings for new phase of Downtown Markham development (Dec 16, 2008)
- Designs for new Corrections Canada office set to begin (Dec 15, 2008)
- Haastown Holdings ready to accept subtrade pricing for Waterscape phase one (Dec 15, 2008)
