November 15, 2006
Opinion
Training requirements for those working with asbestos
As of Nov. 1, 2007 workers and supervisors in Type 3 Asbestos Abatement sites in Ontario will be required to have completed a Training Program approved by the Ministry of Training, Colleges and Universities (MTCU). The specific wording in Ontario Regulation 278/05 reads as follows:
Section 20. (1) the employer shall ensure that,
(a) every worker involved in a Type 3 operation has successfully completed the Asbestos Abatement Worker Training Program approved by the Ministry of Training, Colleges and Universities; and
(b) every supervisor of a worker involved in a Type 3 operation has successfully completed the Asbestos Abatement Supervisor Training Program approved by the Ministry of Training, Colleges and Universities.
Other sub-sections refer to the required documentation of training, permits workers to qualify if they have equivalent training in other provinces and clearly requires that workers or supervisors must have received this training prior to undertaking the Type 3 work.
Due to the need to develop these programs and ensure employers have sufficient time to implement them, this section of O. Reg. 278/05 does not come into force until Nov. 1, 2007.
Several committees, chaired by Michelle Foster-Chandler of the Program Development and Standards Unit of MTCU, have been meeting since January 2006 to develop the training standards.
The members of the steering committee and sub-committees include representatives of abatement and demolition contractors, trade, industry and safety organizations, supervisors and workers (both union and non-union) who perform abatement work, consultants, and the Ministry of Labour.
EACO CORNER
Don Pinchin
The committee decided very early in its deliberations that the mandate of the training was to enable workers to “undertake Type 3 asbestos abatement work safely” and not the broader mandate of teaching workers how to plan and undertake asbestos abatement in the broadest sense.
The MTCU has also made it clear that it was necessary for the committee to complete its work in early 2007. While the steering committee set the direction for training, the content itself was largely determined by Type 3 workers and supervisors in two and three-day meetings which established and validated the program content.
While the work of the committee is not yet totally finished and it is not possible to guarantee that the final documents will not vary slightly from their current status, the following points indicate the current thoughts of the committee:
Once the training programs are completed, they will be widely publicized through the various ministries and trade organizations. Interested parties must ensure they are prepared for Nov. 1, 2007 as this will greatly affect the availability of workers, training costs and costs of abatement.
Dr. Don Pinchin is President of the Environmental Abatement Council of Ontario (EACO) which is represented on the Steering Committee and Sub-Committees.
| MOST POPULAR STORIES |
- New technology allows concrete to come clean
- Ontario architects, general contractor associations issue joint HST bulletin
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Ground broken on the Cathedral Centre in Toronto
- SNC-Lavalin subsidiary Profac under scrutiny over federal contract billing
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $201,737,936,657 that Reed Construction Data Building Reports reported on yesterday.
$300,000,000 Toronto ON Tenders
$150,000,000 Port Hope ON Prebid
$50,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Canadian Construction Association chair bids farewell
- Excavation underway for St. Gabriel Manor condos in Toronto
- Pursuit of LEED could result in professional negligence, insurance executive warns
- St. Marys Cement plant workers go on strike in Bowmanville, Ontario
- Construction continues on the Nautilus at Waterview condo project in Etobicoke, Ontario
- Search continues for sustainable architecture
- U.S. construction unemployment could get even worse
- WorkSafeBC issued record number of fines in 2009
- Canada job numbers up in February
- BC Hydro awards purchase agreements for 19 clean wind, run-of-river energy projects
- Concern over presence of hermit beetles delays Poland road job
- Russian official calls 2014 Winter Olympics protests “unconstructive”
- Construction moving forward on Ho Chi Minh City tunnel
- Government takes over Northwest Territories P3 bridge project
- Canadian construction experts visit earthquake-ravaged Haiti
- Winnipeg gets new water treatment plant
- Weighing in on the Tercon Contractors appeal decision
- Construction restarting on hospital in Fort St. John, British Columbia
- In new movie, Hamilton construction worker becomes ‘Defendor’ at night
- ‘Quality product cannot come from cutting corners on safety’
- Shop owner suing VANOC over pre-Olympics road construction disruptions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- The world financial crisis goes into extra innings (February 25, 2010)
- More