January 19, 2007
UNIVERSITY OF CALGARY
Graduate students at the University of Calgary join Dr. Janaka Ruwanpura in investigating construction industry best practices. From left to right are Fereshteh Mafakheri, Kasun Hewage, Dr. Ruwanpura and Xin Liu.
Innovation
University research takes aim at efficiency
Competitors join forces in unique partnership
In the overheated Calgary construction market, the last thing one would expect from competing companies is collaboration. In a bid to improve industry efficiency, several construction powerhouses are collaborating for a unique research project.
PCL, Graham, EllisDon, Ledcor, Cana, Stuart Olson and Revay and Associates have joined forces with the Calgary Construction Association and the Canadian Construction Research Board to fund a $1.1 million Construction Productivity Improvement research project at the University of Calgary.
The companies provided a collective fund of $450,000 with the federal government’s National Science and Engineering Research Council adding $562,000 and the university contributing $130,000.
Headed by Dr. Janaka Ruwanpura, an assistant professor in Project Management Specialization at the Faculty of Engineering at the University of Calgary, the project’s second phase has already produced impressive results.
The four original industry partners (PCL, Graham, EllisDon and Ledcor) have estimated an initial $50,000 study which began in 2003 has helped them to achieve almost $2 million in efficiencies.
“In the first phase of the study, we looked at what people did on job sites, physically monitoring their time at each activity in a whole range of categories,” says Kees Cusveller, Graham Construction district manager.
“What surprised us was how unproductive we all were. We all suspected this, but never wanted to admit it.”
One of the greatest scheduling bottlenecks was materials management, says Cusveller.
“There was a disconnect between what the guys needed in materials and what the crane was delivering. We now sit down with the foreman and crane operator each morning and tell them what we need and what the sub-trades need at any given time and it’s made us more productive.”
Researchers also found many construction workers knew little about their projects, including how long the project would last, the size of the finished building or what final use of the structure might be. Staff is now briefed on the scope of each project before commencing work.
The second phase of the study will take place over five years and look at more specific issues, including workforce motivation, best practices models for supervision, efficient management of labour, materials, equipment and tools, and labour productivity at the macro level.
Stakeholder companies have identified additional areas of research they’d like to see investigated.
“We’re interested in material handling on a tight site,” says Bob Hildebrandt, vice president of Ledcor’s Calgary office. “There’s a big difference between working on a shopping centre and a downtown office building.”
Ruwanpura says the construction industry isn’t particularly inefficient, but by adopting work practices and new technology it can dramatically improve performance and lower cost overruns.
“Although we were waiting for government funding, some of the research on the second phase had already begun in February of 2006 and we’ve already seen results,” he says. Careful observation of concrete formwork over a 10-week period, for example, has resulted in a 28 per cent improvement in output.
“Our recommendations aren’t rocket science,” says Ruwanpura.
“We’re concentrating on common sense, low-cost solutions to begin with. Once we establish a level of trust, we’ll suggest solutions that might have some higher costs and complexity associated with them.”
| MOST POPULAR STORIES |
| CURRENT STORIES |
- Tower rises at DJ Campbell Construction’s Casa condominium project
- High-school construction teacher fined after dispute with Ministry of Labour inspector
- Enforcement key to protecting road crews, says Ontario Road Builders’ Association
- Restoration Environmental Contractors take down smokestack at former Phillips Cable facility in Brockville
- Treatment of Chinese workers brings union disputes and calls for public inquiry
- Korky Koroluk: Rising price of oil affects more than just the price of gas
- SNC-Lavalin acquires Nova Scotia engineering firm C.J. MacLellan
- SNC-Lavalin wins contract to build two natural gas compressor stations in France
- U.S. manufacturing activity expands, construction spending declines
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Will China be another Japan? (2) (July 4, 2008)
- Will China be another Japan? (1) (July 3, 2008)
- The Export Dependency of Canada’s Provinces (July 2, 2008)
Lifestyle Blog More 
- High Finance, Carrick Family Style (June 30, 2008)
- A Dozen Ways to Lure American Visitors to Canada (June 23, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Menkes sets early 2009 start date for Four Seasons hotel project (Jul 3, 2008)
- Ottawa’s Congress Centre prepares to set green example (Jul 3, 2008)
- York Region plans Keswick odour-control facility (Jul 3, 2008)
- Durham Region plans expansion of transit facility (Jul 3, 2008)
- Vrancor negotiates with City of Oshawa for downtown brownfield site (Jul 2, 2008)
