May 18, 2007
Renewed Concept
Ontario hospitals seek long-term cogeneration project benefits
Cogeneration choices come down to economics
LONDON
Although co-generation is a concept which has been around for some time, financial implications of implementing such a system may have hampered popularity.
Cogeneration, which produces both heat and power from the same fuel and reduces greenhouse emissions by recapturing what would otherwise have been waste energy, hasn’t gained wide scale acceptance, says an industry spokesperson.
“There are parts of North America and Europe that use cogeneration much more than we do in Ontario,” said Jake Brooks, executive director of the Association of Power Producers of Ontario.
Brooks said there has been some growth in the use of the approach, which can harness technology ranging from large-scale gas turbines with heat recovery to considerably smaller internal combustion engines.
A steam turbine (above) at the London Health Sciences Centre (below) seems to be the solution for making cogeneration plants financially feasible in a hospital setting.
A provincial program launched last year set a goal to contract 1,000 megawatts (MW) of power from providers using cogeneration. By the fall of 2006, the program had arranged seven contracts for a total of 414 MW.
Ontario hospitals and universities, which have to access hot water 365 days, 24 hours per day each year and need large quantities of electricity, are starting to consider cogeneration more frequently.
In industrial settings where steam is a primary component of the operation, cogeneration is catching on.
It has been used at the Redpath sugar factory in Toronto since the 1950s and today is a mainstay at the London-based CASCO corn wet milling facility and Labatt Breweries.
But “it’s hard to make it (cogeneration) pay,” Brooks admitted, pointing out that the approach makes more sense in jurisdictions where the costs of electricity are much higher compared to gas.
At the London Health Sciences Centre, the decision to adopt cogeneration was a no-brainer.
“We’ve done cogeneration on this site for close to 20 years, said Joe Chiasson, the hospital’s coordinator of energy services.
The hospital’s first cogeneration venture involved setting up an energy-from-waste plant.
“Technically it worked, but economically it just didn’t fly,” Chiasson said, explaining the tipping fees the plant received from the city were not enough to cover the operation costs and so the facility was shut down in 1999.
Along with the challenges of making the venture economically sustainable came the headaches of having to deal with government red tape, mostly to do with the approval process.
The red tape has improved but still exists today, he said, pointing out requirements for engineering studies to approve a particular installation can be “very expensive and unjustifiably so.”
With the installation last year of a steam turbine it looks like the hospital has found a way to make cogeneration financially feasible.
The steam turbine is in addition to a gas turbine that generates five MW of power. The hot gas goes to a heat recovery boiler to make steam to supply heat for the multi-building facility.
The system is used to generate all of the hospital’s heating and electrical needs in the winter and about half of its electrical needs in the summer. Before the steam turbine, a pressure-reducing valve was used to reduce the steam to the levels needed for distribution in the hospital’s heating system.
By replacing the valve with the steam turbine, not only is the pressure reduced but there is also the potential to generate two additional megawatts.
Introducing the steam turbine last year held few surprises.
It’s the fourth major power plant project at the hospital and “we’re kind of used to it now,” Chiasson said.
The hospital obtained third party financing for the project. It will pay down the debt by using the difference between its previous electricity bills and the new, significantly-reduced bills.
Chiasson anticipated it would take about five to 10 years to complete the payback.
Like Brooks, Chiasson said ultimately, the decision to adopt cogeneration comes down to economics. “Is it cheaper to make some of your own electricity or is it not,” he said.
| MOST POPULAR STORIES |
- Kenaidan keeps steady pace at Barrie Water Pollution Control Centre project
- Missing out on major highway jobs not a concern for SNC-Lavalin, CEO says
- Project manager for Reitmans Canada stays ahead of fickle fashion market
- McMaster study looks at link between diesel fumes and diabetes
- PCL relies on teamwork to get the job done at Maple Leaf Square project
- 20 Most Popular Stories
| CURRENT STORIES |
- Trucks take turns at Tucker HiRise’s Boutique condo site
- Rising materials costs contribute to higher levels of non-residential construction investment
- CSA solicits support for national building deconstruction standard
- VIA plans to invest $25 million to modernize Ottawa-Montreal railway infrastructure
- Bilfinger Berger Canada sues Metro Vancouver over Capilono-Seymour tunnel project
- Eastern Construction digs deep at Li Ka Shing Knowledge Institute site
- Stringent standards help Chino Hills community withstand recent earthquake
- Pace of Canadian job creation likely to slow, economists warn
- Loblaw set to build Regina distribution centre
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Tidbits (1) (August 1, 2008)
- A Big Gamble for Canada’s Aerospace Industry (July 31, 2008)
- Intriguing Ideas to Replace Oil and Natural Gas (2) (July 30, 2008)
Lifestyle Blog More 
- Ode to an Audience (Part 3 of 3) (August 7, 2008)
- Ode to an Audience (Part 2 of 3) (August 6, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Galleries Saint-Hyacinthe to undergo major expansion, renovation (Aug 5, 2008)
- ENMAX ready to break ground on Crossfield Energy Centre (Aug 5, 2008)
- Norson Construction begins renovations to create Vancouver’s first Wal-Mart store (Aug 5, 2008)
- Public Works Canada issues Request for Qualifications for RCMP E-Division headquarters (Aug 5, 2008)
- Terasen ready to select project manager for Lions Gate biogas energy facility (Jul 31, 2008)