LATEST NEWS
July 11, 2007
VINCE VERSACE
Work continues on the $1 billion Goreway Station construction site which employs 800 workers and 47 sub-contractors on the project. When completed, this will be first new major power plant built in Ontario in past 25 years.
Industrial
Electrifying project shocks all
Communication key to keeping Goreway online
A key to tracking the beehive of activity at the Goreway Station build, one of Ontario’s biggest construction projects, is constant communication, says the site’s construction manager.
“This is the Rolls Royce of power plants,” says Mike White, SNC-Lavalin Power Ontario construction manager. “The co-operation among all the trades has been fantastic.”
The Goreway Station is the first new major power station built in Ontario over the last 25 years. SNC-Lavlin is carrying out the engineering, procurement and construction of the plant which has a $1 billion price tag. The 875 MW plant will be Canada’s largest combined cycle power station, fuelled by natural gas. When it is completed and running at full capacity, it will meet the power needs of over 330,000 homes. Sithe Global Power was chosen by the Ontario Power Authority and the Ontario government to build the plant.
“Working on a project like this is fun,” says White. “It is a large site with overlap between the sub-contractors. Site scheduling and coordination is a daily adventure.”
VINCE VERSACE
Fixtures await to be raised to the ceiling of the air condensing complex at the Goreway Station plant. There will be 35 fans mounted to help cool off steam exhaust created during the power generation process.
There are 47 sub-contractors on the 20 hectare site in Brampton. Only 21 per cent of the site will actually be occupied by the plant when it is completed.
The project employs 800 workers from numerous construction trades. The site has become a model for inter-related building in the eyes of the Ministry of Labour, says White. The labour ministry has begun sending some of its newcomers for training at the site to learn about all the trades and construction.
“It is like a big jig-saw puzzle and we do six-week lookouts to see where we are going,” adds White. “There is a huge scope of work here with a lot of overlap.”
Each day of work can move the project forward by three to four per cent. The plant was expected to provide “simple cycle” power this June but the bankruptcy of one of SNC’s key equipment suppliers caused a delay in the rollout of that phase.
The recent three-week labourers’ strike also closed things down for seven days due to to jobsite work conditions. The strike put the project about a month behind schedule. Completion of the plant is still targeted for the end of 2008.
Health and safety training and reporting plays a major role daily, says White.
Goreway hosted a Hong Kong government delegation this past April which focused on health and safety and the construction process. When the representatives were asked why they chose Ontario and this particular project, the answer was that they wanted to “see the best.”
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Caterpillar dispute a factor in CAW-CEP union merger talks
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Future unclear for price of iron ore, scrap steel, rebar
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 333 projects with a total value of $7,273,203,495 that Reed Construction Data Building Reports reported on Thursday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$80,000,000 North York ON Tenders
CONDOMINIUM APARTMENT BUILDING, RETAIL
$75,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Ontario Road Builders’ Association focused on partnerships at convention
- Construction continues on the Regent Park Aquatic Centre in Toronto
- BML Multi Trades president Jim DiNovo takes helm of Hamilton-Halton Construction Association
- Seeing the sustainable forest for the trees
- Steel hurdles for Aga Khan Museum build
- Milton, Ontario council approves velodrome for 2015 Pan Am games
- ASHRAE, International Association of Plumbing and Mechanical Officials plan to cooperate on codes, standards
- MOD Developments 60-storey Massey Tower to include restoration of 1905 Toronto bank
- ERA Architects to conduct study for possible heritage district in Picton, Ontario
- Burlington, Ontario announces preferred hospital redevelopment site
- Bing Thom Architects to design Surrey Performing Arts Centre
- Wind farm contract awarded
- Opposition grows after deal collapses
- $1.8 billion in improvements planned for Vancouver airport
- When low bidders sue over contracts
- North Vancouver condos take shape
- U.S. firms expect fewer layoffs in 2012
- Maple Leaf Gardens time capsule discovered
- A look at Canada's historic concrete ship
- Partnership announced between File Hills Qu'Appelle Tribal Council and Graham Business Trust
- Mike Holmes-designed community in Alberta gets go ahead
- Province of British Columbia contributes cash to green energy projects
- Program for upcoming apprenticeship forum released
- New VRCA chair elected
- Construction union wage index remains the same
- Alberta government orders immediate site remediation
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








