Construction Law
Contractors should benefit from new, less-ambiguous Waiver of Claims provisions in CCDC2
The Waiver of Claims provisions of the old CCDC2 have always been problematic. The old clause provided a broad waiver of claims by the Owner except for those claims that the Owner had made in writing prior to Substantial Performance.
The only exceptions to that waiver were warranty claims, indemnification claims and claims with respect to “substantial defects and deficiencies.” With respect to these latter claims the limitation period was six years.
Norm Streu
Construction Law
A difficulty with this provision from the Contractor’s perspective was that it was invariably amended by way of Supplementary General Condition. More generally, the provisions were unclear and consequently were rarely relied upon.
The new CCDC2 Waiver of Claims is far less ambiguous and includes some important amendments.
The new clause now limits the waiver and release of both the Owner and the Contractor to claims which they had knowledge of or “reasonably ought to have knowledge” of at the time of Substantial Performance. If the Owner or Contractor does not have knowledge of the circumstances of a claim, and could not reasonably be expected to have such knowledge, there is no waiver or release.
This language is far more reasonable and in fact was frequently included in Supplementary General Conditions to the old version.
Claims for “substantial defects or deficiencies” are still released six years after Substantial Performance. The waiver and release at the end of six years is “absolute” in the sense that it is not limited to claims that are known or reasonably ought to be known after the expiry of six years.
Claims for warranty work, or other work performed after Substantial Performance, are now released 395 calendar days after Substantial Performance.
The old CCDC2 did not include any definition of what was meant by a “claim made in writing” before the applicable period. There were frequent disputes as to whether a particular communication was a “notice in writing” pursuant to these provisions, thereby nullifying the release that otherwise would have occurred.
The new CCDC2 seeks to correct this problem by clearly delineating what must be included in a “Notice in Writing of claim.” The notice must include:
A clear and unequivocal statement of the intention to claim;
A statement as to the nature of the claim and the grounds upon which the claim is based; and,
A statement of the estimated quantum of the claim.
Another problem that frequently arose under the old language was created by the link of waivers and releases to the final certificate for payment. Under the old CCDC2, claims made in writing prior to the issuance of the final certificate were never waived or released.
In situations where a problem arose at the end of a project and the final certificate was withheld, there was an argument that there had been no waiver or release of any claims.
Under the new CCDC2, the trigger date for the release of claims is the sixth calendar day before the expiry of the lien period.
This provision provides greater certainly to the release date and ensures that claims are brought forward before the holdback is released.
Norm Streu is a partner in the Construction & Engineering Group of the Vancouver law firm Alexander Holburn Beaudin & Lang LLP. Streu is a past chair of the Vancouver Regional Construction Association. He will be writing a series of columns for Daily Commercial News on the impact of the new CCDC2 document.
| MOST POPULAR STORIES |
| CURRENT STORIES |
- Aerialists soar at groundbreaking celebration for Four Seasons Hotel and Private Residences
- More Ontario workers register as apprentices, but rate of completion declines
- China’s construction market offers opportunities, challenges for contractors
- FER Building Solutions plans restoration for Prince Rupert’s historic CN building
- Vanbots oversees smooth progress of Bramalea City Centre Mall project
- Use of dispute resolution services rises in competitive construction market
- TransCanada and ConocoPhillips plan to extend Keystone pipeline to U.S. Gulf Coast
- Refurbishment of Dahla dam could make it a target: defence analyst
- Lack of training blamed for death of Canada Line mobile-crane operator
- Quebec teen dies in collapse of garage under construction
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Some Other Keys to Commodity Pricing (2) (July 18, 2008)
- Some Other Keys to Commodity Pricing (1) (July 17, 2008)
- There are Exciting Answers to the World’s Food Shortage (July 16, 2008)
Lifestyle Blog More 
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
- Which Letter of the Alphabet is the Funniest? (July 7, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- George Brown College wins $61.5 million in provincial funds for Toronto Waterfront campus (Jul 14, 2008)
- Plans get underway for Saline Creek Plateau and Parsons Creek communities (Jul 14, 2008)
- Life Construction seeks trade prices for 500 on Sherbourne condominium project (Jul 14, 2008)
- Working designs nearly complete for Joseph and Wolf Lebovic Jewish Community Campus (Jul 11, 2008)
- Alberta commits $200 million to Federal Building renovation and redevelopment (Jul 10, 2008)