March 27, 2008
ELAINE DELLA-MATTIA
Palmer Construction crews have been busy this winter servicing a site in the east end of Sault Ste. Marie that will house a small residential subdivision. Record cold temperatures and higher-than-average snowfall accumulations have been the largest challenge of the winter project. Construction on the homes, to be built by Sal Dan Construction, is to begin this spring.
Planning
Northern Ontario’s short construction season poses challenges
Of all the differences between the north and the south when it comes to construction, one factor has the biggest impact on sewer and watermain projects – the north’s short building season.
Palmer Construction Group Inc. president Terry Rainone can rhyme off a handful of other differences, but the short construction season is always top of mind. “We usually don’t get to start until the mid or end of May because that’s when the frost is finally out and by the end of October we’re wrapping things up. Sometimes, depending on the weather, we get lucky and have until mid-November,” he said.
About 30 per cent of Palmer Construction’s work is sewer and watermain; most of that in Sault Ste. Marie. While the majority of that work takes place over the short spring to fall construction season, projects can be done in the winter, he said.
“Northern Ontario construction is more challenging than that in the south but if you keep your nose to the grindstone, you can make a success of it,” he said.
The company is currently working on a winter sewer project to service a small residential subdivision that will be developed by builder Sal Dan Construction this spring.
Rainone said that winter site servicing requires more effort than for a summer project. Shorter work days are colder and daily tasks often include snow removal before servicing work can begin, he said.
“The frost is something we need to contend with and it’s something that slows down the production as well,” he said.
While summer construction projects can mean stockpiling material and locking up machinery and equipment on site at the end of the day, winter projects differ. Materials targeted for use on any given day are brought in on a daily basis.
Mobile equipment is returned to the company’s yard to ensure it will start properly the next day, and larger equipment may face mechanical issues due to the cold and snowy nights.
“It drives up costs and it means more time, more work,” he said. Rainone said work crews must also be diligent when laying pipe to ensure it is properly placed in the bed and that frost or frozen chunks of earth are removed.
Since the company also runs snow removal operations, drastic amounts of snowfall often shut down construction sites for days at a time, he said.
Palmer Construction Group Inc. resulted from the amalgamation of Palmer Paving and Kember Construction in 2000, five years after Rainone was named president of Palmer Construction.
Palmer’s specialty was paving and site servicing while Kember specialized in commercial building construction and renovation. The amalgamated company allows for turn-key operations on all construction sites.
Rainone expects the construction season to be a good one for his company and its 55 employees this year while the city continues to bask in a construction boom.
“We’ve had a strong number of good years and a lot of company growth,” he said. “We’ve got new people, new equipment, but we’re keeping an eye on how much longer it’s going to last. What happens in the U.S. and southern Ontario are often indicators that we gauge.”
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 425 projects with a total value of $5,472,383,138 that Reed Construction Data Building Reports reported on Tuesday.
$660,000,000 Marmora and Lake Twp ON Prebid
$200,000,000 Kingston ON Prebid
$105,000,000 Oshawa ON Prebid
| CURRENT STORIES |
- Where does labour law stand on ladder safety?
- Construction continues on the MaRS Centre Phase II in Toronto
- Bending Lake Iron Ore pushes ahead with mining plans
- Reserve Properties continues plans for 109OZ condos in Toronto
- Ontario courts rule against owners rejecting low bids using undisclosed criteria
- Westray disaster 20th anniversary a call to safety action
- Dirt moves as Saskatchewan announces highway work
- Worker hurt in dressing room ceiling collapse at Edmonton stadium
- IBI Group raises $40.5 million from stock issue
- Plazacorp to spend $12.2 million on retail property development in 2012
- Ottawa to proceed with preliminary Lansdowne Park construction work, short-lists PCL, EllisDon and Pomerleau
- VIDEO: Highlights from the May 17 Daily Commercial News
- VIDEO: Common ladder safety errors in construction
- High School Construction
- Victoria bridge inches closer to construction
- Collapse injures worker at Commonwealth Stadium
- Panel appointed to oversee hearings into B.C. mine project
- Bockstael celebrates 100 years
- More work needed to protect flaggers
- Co-founder of ATCO announces his intention to step down as chair
- SNC-Lavalin hit with $1.5 billion class action lawsuit
- PST returns to British Columbia
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More