Boutique Phase l condominium project in Toronto.

WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

Work continues below grade at phase one of the Boutique condominium project in Toronto.

Tucker HiRise oversees work below grade at the Boutique

Tucker HiRise is the project/construction manager on the 16 storey, 333-unit Boutique project. The work includes guest suites, five levels of underground parking and ground-floor retail space.

The project was designed by ZAS Architects Inc. for owner Simcoe Nelson Property Inc.

Consultants are Jablonsky Ast & Partners (structural); United Engineering Ltd. (mechanical/electrical); Cecconi Simone Inc. (interior); and Ferris & Associates (landscape).

Subtrades include Aro Excavating Ltd.; Deep Foundations Contractors Inc. (shoring/caissons); Delgant (civil) Ltd. (formwork); Innocon Inc. (concrete supply); Global Plumbing & Heating Ltd.; and Nortown Electrical Contractors Associates.

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 273 projects with a total value of $4,217,286,523 that Reed Construction Data Building Reports reported on Wednesday.

VEHICLE FUELING STATIONS

$1,000,000,000 Province of Ontario ON Prebid

CONDOMINIUM APARTMENT BLDG, RETAIL

$60,000,000 Toronto ON Prebid

POLICE HEADQUARTERS FACILITY & DISTRICT FACILITY

$60,000,000 Niagara Falls ON Prebid

Daily Top 10

CURRENT STORIES
ALEX’S ECONOMICS BLOG

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

TODAY’S TOP JOBS

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design