LATEST NEWS
Roadbuilding | Steel | Heavy Equipment | Concrete | Trade Contracting
April 28, 2008
RICHARD GILBERT
This rebar tower fell over during construciton of the Pitt River bridge just outside Vancouver. Repairs to replace it will be part of the job’s contract price.
Rebar fall won’t delay Pitt River bridge job
Crane body contacted guy wire, ministry investigation reveals
Vancouver
Workers building the new Pitt River Bridge are assessing the damage and developing a plan for repairing the structure after a rebar column toppled.
A nine-metre tower of rebar, which will form one of the support pylons for the bridge, fell over in the early hours of April 14 when a crane came into contact with a guy wire.
The B.C. Ministry of Transportation owns the bridge and the general contractor is Peter Kiewit Sons Co.
At about 6:30 on the day of the incident, one of the supports was damaged and a tower of rebar fell over. Initial reports indicated that one of the guy wires holding the rebar in place was severed by a crane operator and another one was hit.
However, Ministry of Transportation spokesperson Susan Williams says that wasn’t the case.
“The crane did not cut the guy wire. The crane body came in contact with one of the corner guy wires, pulling the cage over,” said Williams. “The crane was not performing a lift at the time of the incident. It was being repositioned.”
No one was hurt in the incident.
“The structural engineers and designers are reviewing the condition of the pylon and rebar, and working with Kiewit to provide a suitable repair procedure which will ensure the structural integrity of the bridge,” Williams said in an e-mail.
“Any concrete damage was minor in nature and can be repaired with standard procedures to allow the next lift to be poured on top as planned.”
Repairs are underway and are expected to continue without affecting construction on the rest of the site.
“The detailed repair procedures are still to be determined, but will likely include straightening and appropriate testing of the lower bars, fabrication of a new rebar cage and minor surface repairs to existing concrete,” Williams said.
Despite this setback the bridge is scheduled for completion in late 2009.
“The remaining five pylons are proceeding on schedule without impact,” she said.
“Any delay to the damaged pylon will be recovered by bringing in additional resources and working extra shifts if necessary, such that the overall bridge schedule will not be impacted.”
The ministry also said it was not possible for the nine-metre tall rebar tower to fall into traffic on the old bridge running through the construction site.
“It (the rebar lift) is mechanically coupled to the previous rebar lift which is in turn embedded in concrete,” explained Williams.
“The couplers are stronger than the bars themselves, so bending over of the cage in place is the worst that could occur.”
The cost of the repairs is not known at this time. The contract is a lump sum, fixed-price contract and as such, any repair costs are included in the contract price.
The contractor is in the process of building part of each of the six supports for the bridge deck. The supports are built by pouring concrete into stacked rebar cages.
The old Pitt River Bridge is a swing bridge that spans the Pitt River between Port Coquitlam and Pitt Meadows, B.C.
| MOST POPULAR STORIES |
| CURRENT STORIES |
- Aerialists soar at groundbreaking celebration for Four Seasons Hotel and Private Residences
- More Ontario workers register as apprentices, but rate of completion declines
- China’s construction market offers opportunities, challenges for contractors
- FER Building Solutions plans restoration for Prince Rupert’s historic CN building
- Vanbots oversees smooth progress of Bramalea City Centre Mall project
- Use of dispute resolution services rises in competitive construction market
- TransCanada and ConocoPhillips plan to extend Keystone pipeline to U.S. Gulf Coast
- Refurbishment of Dahla dam could make it a target: defence analyst
- Lack of training blamed for death of Canada Line mobile-crane operator
- Quebec teen dies in collapse of garage under construction
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Some Other Keys to Commodity Pricing (2) (July 18, 2008)
- Some Other Keys to Commodity Pricing (1) (July 17, 2008)
- There are Exciting Answers to the World’s Food Shortage (July 16, 2008)
Lifestyle Blog More 
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
- Which Letter of the Alphabet is the Funniest? (July 7, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- George Brown College wins $61.5 million in provincial funds for Toronto Waterfront campus (Jul 14, 2008)
- Plans get underway for Saline Creek Plateau and Parsons Creek communities (Jul 14, 2008)
- Life Construction seeks trade prices for 500 on Sherbourne condominium project (Jul 14, 2008)
- Working designs nearly complete for Joseph and Wolf Lebovic Jewish Community Campus (Jul 11, 2008)
- Alberta commits $200 million to Federal Building renovation and redevelopment (Jul 10, 2008)
