April 30, 2008
Steel bunker will encase Chernobyl reactor
20,000-tonne arch will slide over existing sarcophagus
KYIV, Ukraine
Twenty-two years after the Chernobyl nuclear disaster, work is underway on a colossal new shelter to cover the ruins and deadly radioactive contents of the exploded Soviet-era power plant.
For years, the original iron and concrete shelter that was hastily constructed over the reactor has been leaking radiation, cracking and threatening to collapse. The new one, an arch of steel, would be big enough to contain the Statue of Liberty.
Once completed, Chernobyl will be safe, said Vince Novak, nuclear safety director at the European Bank for Reconstruction and Development which manages the $505 million project.
The new shelter is part of a broader $1.4 billion effort financed by international donors that began in 1997 and includes shoring up the current shelter, monitoring radiation and training experts.
The explosion at reactor No. 4 on April 26, 1986 was the world’s worst nuclear accident, spewing radiation over a large swath of the former Soviet Union and much of northern Europe. It directly contaminated an area roughly half the size of Italy, displacing hundreds of thousands of people.
In the two months after the disaster, 31 people died of radioactivity, but the final toll is still debated. The World Health Organization estimates that about 9,300 will eventually die from cancers caused by Chernobyl’s radiation. Groups such as Greenpeace insist the toll could be 10 times higher.
The old shelter, called a “sarcophagus,” was built in just six months. But intense radiation has weakened it, according to the U.S. Nuclear Regulatory Commission, and rain and snow are seeping through cracks.
Officials say a tornado or earthquake could bring down the shelter, releasing clouds of poisonous dust.
The first step, shoring up the sarcophagus, is almost complete, Ukrainian and EBRD officials say.
Later, the 20,000-tonne arch — 105 metres tall, 255 metres wide and 150 metres long — will be built next to the old shelter and slid over it on railtracks.
Its front side will be covered by metal, and the back will abut the wall of reactor No. 3. Construction is to begin next year and be completed in 2012, and it is designed to last 100 years. It is designed and built by Novarka, a French-led consortium.
Workers will wear protective suits and masks, and those needing to be closer to the radioactivity will work in shifts as short as several minutes.
Once the arch is up, the least stable parts of the old shelter and the reactor will be dismantled and removed. In 50 years, the nuclear fuel will be extracted, although it is unclear where it will be stored.
The EBRD says 95 per cent of the reactor’s nuclear inventory is still inside the ruins, but some experts believe most of the radiation was released in the days after the accident.
The new shelter evokes mixed feelings among Ukrainians. Some are just happy the reactor is finally going to be made safe. Others, especially those directly affected by the disaster, accuse the government of playing up the new shelter at the expense of treating their health problems.
Scientists continue to debate the Novarka solution, with some saying the reactor should be dismantled or embedded in concrete. Others say the government should be more concerned about the contaminated land, ground water and the spent nuclear fuel.
Associated Press
| MOST POPULAR STORIES |
- Steel hurdles for Aga Khan Museum build
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- York Region, Ontario approves subway construction expenditures
- Toronto Construction Association presents ‘Best of the Best’ awards
- Bidding closes for Toronto 2015 Pan Am games venues
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $1,890,889,993 that Reed Construction Data Building Reports reported on Thursday.
$65,000,000 Toronto ON Negotiated
RETIREMENT RESIDENCE, COMMUNITY CENTRE
$45,500,000 Toronto ON Negotiated
$40,000,000 Brampton ON Prebid
| CURRENT STORIES |
- Steel truss system helps reduce construction cost of Toronto apartment building
- Ontario College of Trades will drive up infrastructure costs: Conservative leader Tim Hudak
- What comes next after green building?
- Procurement needs to be fair, open and transparent
- Losing bidder bridles at Pan Am Games park selection, Equine Canada “thrilled”
- Armstrong extended at Ontario College of Trades
- CVTech secures Hydro Quebec construction, maintenance work
- Toronto council votes in favour of light rail transit
- Ottawa City Council approves affordable housing capital projects
- Pre-cast concrete segment falls into river after gantry crane collapses
- Alberta throne speech hints at development plan
- Union claims construction oversight needed at defence department
- Site prep in North Vancouver
- Legislation limiting strikes ruled unconstitutional
- World Plumbing Day garners support from Canadian senator
- PHOTO GALLERY: Merit Alberta open house
- Seeing the sustainable forest for the trees
- Pump Station Upgrades
- Labour federation opposes pipeline
- Site for new correctional facility selected
- Edmonton roofer dies
- Regulators approve oilsands facility expansion
- Highway 3 upgrades
- New chairman named for Alberta Construction Association
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Home starts and job levels diverge in Canada and the U.S. (February 8, 2012)
- Canada’s labour market flat in January but U.S. on a roll (February 3, 2012)
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- More