Kinder Morgan completes Jasper section of Anchor Loop pipeline project
CALGARY
Kinder Morgan Canada has completed the construction and commissioning of the Jasper section of the Anchor Loop project.
The new 97 kilometres of 30 and 36-inch pipeline, in addition to two new pump stations, will increase the capacity of the Trans Mountain pipeline system.
The $485 million Anchor Loop project is the second major expansion phase of the Trans Mountain pipeline system. It will increase the system’s capacity from 260,000 barrels per day to 300,000 barrels per day by the end of 2008.
DCN News Service
| MOST POPULAR STORIES |
- Construction team ready to raise cranes at Toronto site of Trump International Hotel & Tower
- Canada Green Building Council plans first-ever national summit
- Concrete-pump simulator offers state-of-the-art training for operating engineers
- Shane B. oversees work on St. Gabriel Village’s dome roof
- Wal-Mart Canada announces construction plans for 2008
- 20 Most Popular Stories
| CURRENT STORIES |
- Buttcon builds bus-repair shop in Streetsville
- GM president sees better times ahead for auto manufacturer
- High-tech restoration saves historic Alton Mill from wrecker’s ball
- Authentic architecture addresses social and economic differences
- Sharp-shooters from Southwest Contracting take on Calgary project
- Experts still looking for cause of Houston-area sinkhole
- Rising prices for materials, labour push Thailand’s transit-project costs up
- SMART Papers builds co-generation facility at Ohio plant