DCN ARCHIVES

July 11, 2008

The Avenue condominium project at Avenue Road and St. Clair Avenue West in Toronto.

WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

Concrete pouring progresses at the Avenue condominium project at Avenue Road and St. Clair Avenue West in Toronto.

Crews pour it on at Toddglen Avenue condominium project

Construction manager Toddglen Avenue Ltd. began the 19-storey, 73-unit Avenue Condominium project, which was designed by Page + Steele Inc., in November 2006. Completion is scheduled for January 2009.

Consultants are Jablonsky Ast & Partners (structural), MCW Consultants Ltd. (mechanical/electrical), and PD3 Planning & Design Solutions (landscape).

Subtrades include Four Winds Construction (underground drainage); Anpro Environmental Group Inc. (excavation); Bermingham Construction Ltd. (shoring/caissons); Gilbert Steel Ltd.; Highview Forming Inc.; OZZ Corp. (electrical) and University Plumbing & Heating.

Print | Email | Comment

ALEX’S BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.

Economics Blog    More 

Lifestyle Blog    More 

PROJECT NEWS BRIEFS

FEATURED CAREER AD

Senior Estimator

ON - Toronto

More careers...