August 28, 2008
STANTEC
The City of Toronto will rely on odour control technology that has a proven track record, when it comes to its Ashbridges Bay facility. The facility is large and reliability is a key element to its design and construction.
Tender Issued
Ashbridges Bay Treatment Plant in Toronto set to upgrade odour control
Contract will likely include many elements
toronto, ON
The City of Toronto has released its schedule of RFPs for engineering services on its planned upgrades to the odour control facilities at the Ashbridges Bay Treatment Plant near Coxwell Avenue and Lakeshore Boulevard.
The likely multiple contract RFPs will include:
An RFP with an estimated capital cost of $72 million was put out last month for the facility’s preliminary treatment building upgrades, including a new grit handling system, new screens, new enclosed truck loading bays, a new ventilation and heating system, new bio-filter and stacks and the covering of some primary tanks and venting to the new biofilter.
A further RFP with an estimated $76 million value, currently not on the schedule, involves aeration tank upgrades, including the installation of a fine air bubble diffuser and two contracts for the construction of 11 tank covers.
The construction projects centre on the control of odours emanating from the wastewater treatment plant to less than one odour unit — the standard measurement of odour intensity — beyond the facility’s property limit. A 2002 study commissioned by the city identified the plant’s aeration system as the source of most nuisance odours in the neighbourhood.
The contracts for the projects, except for the P Building upgrade, will be managed and awarded by Earth Tech Canada Inc. and Stantec Consulting Ltd.
No consultant has been chosen to manage a future project that will involve further covering of P Building tanks.
“The construction contracts will be awarded by conventional public tender,” says Frank Quarisa, Director, Wastewater Treatment, City of Toronto. “We have no intention at this time to introduce a pre-qualification process or any other variation on the traditional public tendering approach utilized by the city.
“Given the amount of operational co-ordination that will be required and the number of technical design issues that will need to be addressed, we want to keep our contractual relationship with the successful contractors as streamlined as possible.”
Quarisa says the facility will rely on odour control technology that has a proven track record. “The D building biofilter will be proven state-of-the-art and based on extensive pilot studies conducted on site,” he says. “The Ashbridges Bay facility is large and complex and therefore our focus is on reliability.
“The emphasis throughout will be on selecting and designing based on the best available technologies that have proven records of performance.”
Because some technology will be tested in pilot projects, the design component of the upgrade will require a considerable investment of time.
“We don’t expect construction until 2011 and 2012,” says Quarisa. “When work commences, it will include a heavy emphasis on all the traditional civil, mechanical and electrical disciplines required to work in a wastewater plant.
“All the work will be tendered to general contractors and we don’t anticipate any specialty contracts at this time. Some of the contracts could include asbestos abatement as a significant portion of the work, for example as part of the aeration tank emission air contract, but this will be left with the general contractors to coordinate.”
| MOST POPULAR STORIES |
- Commodities slump puts demolition firms in tight squeeze
- Pair of massive cranes spotted at Vanbots’ Mount Sinai Hospital project
- Canadian Council for Public-Private Partnerships announces winners of national P3 awards
- Dialogue necessary when deciding who should bear P3 project risk, panel members agree
- EnCana and Petro-Canada likely to curb capital spending in 2009
- 20 Most Popular Stories
| CURRENT STORIES |
- Design of Fifth Town Artisan Cheese factory showcases concrete’s versatility
- 2008 Ontario Concrete Award Winners
- Construction organization needs to move beyond union/non-union rhetoric, report says
- City of Ottawa donates land for Algonquin College expansion project
- Total value of Canadian building permits drops 15.7% in October 2008
- EnCana and Petro-Canada likely to curb capital spending in 2009
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Canada’s Recession, the Economic Statement and Coalition Government (December 1, 2008)
- The United States will be a Leader in Deflationary Price Drops (November 28, 2008)
- New and Existing Home Prices Moderate as Economy Contracts (November 25, 2008)
Lifestyle Blog More 
- The Curious Meanings of some Canadian place names Continued (December 1, 2008)
- A Mathematical Proof that Economists are Sexy (November 21, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rio Tinto Alcan invests in new run-of-river hydro project at Shipshaw power station (Nov 27, 2008)
- Graziani + Corazza Architects Inc. near completion of working drawings for Aura at College Park (Nov 26, 2008)
- Roseau River First Nation seeks private investors for community medical office (Nov 26, 2008)
- Ventin Group readies working drawings for Goodes Hall at Queen’s University (Nov 26, 2008)
- Major redevelopment planned for Lloydminster Hospital (Nov 26, 2008)
