September 18, 2008
The feedermain under construction in Peel will deliver water from the Lorne Park Water Treatment Plant on Lake Ontario to the Herridge Reservoir and Pumping Station.
Rapid residential growth and demand for water drive Herridge feedermain project
The rapid residential growth of Mississauga and Brampton is the driving force behind a major watermain investment by Peel Region.
Not only will the six-kilometre-long, three-phase $90-million Herridge Feedermain now under construction in south Mississauga require considerable tunnelling, the 2,100-mm diameter pipe is considerably larger than most watermains.
“That’s fairly large,” says Jeff Hennings, project manager with Peel Region’s environment, transportation and planning services section.
The feedermain is necessary to deliver water from the Lorne Park Water Treatment Plant on Lake Ontario to the Herridge Reservoir and Pumping Station. Its purpose is to increase water delivery to the west half of Mississauga and Brampton.
“Peel is evolving into a new phase as urban centre and the increased water supply is needed to allow communities to function,” says Hennings.
To meet the demands of future development in the region, a separate project to expand the treatment capacity of the plant from 347 to 500 million litres of water daily is getting underway, he points out.
UMA Engineering Ltd. is the consulting engineer for the feedermain project, which has been divided into three contracts.
Earlier this summer C & M McNally Engineering Corp. began the shaft construction to tunnel 2.7 kilometres of pipe from the plant to Lakeshore Road and then to Southdown Road. The pipe will be buried at a depth ranging from 60 to 90 feet, says Hennings.
From that point, another 1.8 kilometres of pipe will tunnelled under Southdown Road to the Queen Elizabeth Way by McNally Construction Ltd.
Shaft construction has also started. Both phases will be completed in early 2010, he says
The third contract will be tendered this fall and will be comprised of both open-cut and tunnel work. While the pipe has to be tunnelled under the QEW, open-cut construction will be used for the remainder of the route, which includes going through a school property and a utility corridor. This phase will be completed late in 2009.
While open construction is more economical, the project’s extensive tunnelling component is necessary to minimize traffic congestion and inconvenience to local residents.
The project was divided into three phases to make it more manageable and to obtain more competitive pricing from contractors, says Hennings.
“There are probably only one or two companies capable of taking on the entire project.”
| MOST POPULAR STORIES |
- Steel hurdles for Aga Khan Museum build
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Toronto Construction Association presents ‘Best of the Best’ awards
- Bidding closes for Toronto 2015 Pan Am games venues
- Steel key for CF-5 fighter jet monument at Toronto defence facility
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 288 projects with a total value of $2,181,603,356 that Reed Construction Data Building Reports reported on Friday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$107,557,000 Burlington ON Tenders
CONDOMINIUM APARTMENT BUILDING
$31,300,000 Toronto ON Prebid
| CURRENT STORIES |
- Steel truss system helps reduce construction cost of Toronto apartment building
- Ontario College of Trades will drive up infrastructure costs: Conservative leader Tim Hudak
- Procurement needs to be fair, open and transparent
- Losing bidder bridles at Pan Am Games park selection, Equine Canada “thrilled”
- Armstrong extended at Ontario College of Trades
- CVTech secures Hydro Quebec construction, maintenance work
- Toronto council votes in favour of light rail transit
- Ottawa City Council approves affordable housing capital projects
- Pre-cast concrete segment falls into river after gantry crane collapses
- Alberta throne speech hints at development plan
- Union claims construction oversight needed at defence department
- Site prep in North Vancouver
- Legislation limiting strikes ruled unconstitutional
- World Plumbing Day garners support from Canadian senator
- PHOTO GALLERY: Merit Alberta open house
- Seeing the sustainable forest for the trees
- Pump Station Upgrades
- Labour federation opposes pipeline
- Site for new correctional facility selected
- Edmonton roofer dies
- Regulators approve oilsands facility expansion
- Highway 3 upgrades
- New chairman named for Alberta Construction Association
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Home starts and job levels diverge in Canada and the U.S. (February 8, 2012)
- Canada’s labour market flat in January but U.S. on a roll (February 3, 2012)
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- More








