February 27, 2009
WILLIAM CONWAY / PROGRESS PHOTOGRAPHY
The $32-million realignment of Dufferin Street in Toronto’s west end will see the use of a cast-in-place concrete tunnel serving four lanes of north-south traffic.
Infrastructure
Toronto’s zig-zagging Dufferin Street ready for realignment
toronto
It may be a historic bend in the road, but there won’t be any tears of nostalgia when the $32-million realignment of Dufferin Street in Toronto’s west end is completed.
The maddening and abrupt southern end of the north-south street, which has a pair of hooks to make it a traffic bottleneck and is a headache for local residents, is about to undergo a massive transformation to straighten it out.
The plan is to realign the thoroughfare south of Queen Street West, where it currently terminates for traffic coming north. Motorists coming from the Gardiner Expressway and the Canadian National Exhibition ground – and all those Toronto F.C. fans heading home after the game – must make a series of zig zag turns on several streets to get back to Dufferin Street again.
The situation has been created through some unusual planning brought on by a railway right of way.
The grade separation dates to 1884 and eliminating it has been on the books since 1966. But the project never before made it to the top of the priority list.
As such, the configuration has been a thorn in the community’s side for decades. City structural engineer Jim Schaffner says connecting the stub of Dufferin Street on the north side to the tail end on the south side at Queen St. West will return Gladstone Avenue and Peel Street to the local residents and relieve it of the heavy traffic it currently experiences.
Dufferin Construction won the $25-million contract to build an underpass which will require lifting a steel girder rail bridge across Queen Street West a metre or so to allow some modifications without disrupting CN and GO train service. The bridge will then be lowered back down.
Site preparation is already under way and work is expected to stretch through the summer into next winter with completion by December 2009. Ancillary projects include items such as landscaping, art, bicycle lanes and lighting.
“There are some blackout days they can’t interfere with traffic because of events and the CNE,” says Schaffner. “But they’re an experienced company and they should have no problems.”
The cast-in-place concrete tunnel will carry two northbound and two southbound lanes of traffic with sidewalks and bicycle lanes. The walls will be adorned with public art, which a committee is currently investigating, says Schaffner.
Concrete was chosen as the preferred method of construction because it allowed minimum structural depth between rail and structural soffit, minimum visual intrusion and material requirements, minimum risk and the shortest construction period. It was also the most cost effective solution.
“It’s going to be a challenge,” says Eddy Marin, Dufferin Construction’s district manager. “The bridge work is being done by CN but we have to work around the trains, the traffic in the city there – which is brutal – and I think the biggest challenge will be around the underground utilities in the area.”
Still, he says, when complete the area will get a much needed esthetics boost.
“It really is going to look beautiful when it’s done,” he says. “We got the start authorization Dec. 1 and we figure on finishing by spring 2010.”
The grade rises quickly from south to north just as to roadway exits the tunnel and the rail line overhead limit the height of the tunnel which could impact CN and Toronto hydro maintenance and lighting requirements.
On the south side it will also open up what is essentially wasted industrial land to redevelopment and landscaping, providing the area with some much needed gentrification, a process which has been ongoing for the last five years with the renovation of the Drake and Gladstone hotels and the burgeoning artist and young urban population.
In addition to improved traffic flow and safety, benefits include better transit speed, increased emergency vehicle access and response times, better air quality, lower noise levels and a savings of 250,000 litres of fuel because drivers won’t be stuck idling in traffic jams.
| MOST POPULAR STORIES |
- Construction moving forward on Ho Chi Minh City tunnel
- Deaths of five immigrant workers changed jobsites forever
- Pride, sadness as Hogg's Hollow memorial unveiled
- St. Marys Cement plant workers go on strike in Bowmanville, Ontario
- ‘Sandhogs’ who perished had diverse personal stories
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 371 projects with a total value of $1,380,346,147 that Reed Construction Data Building Reports reported on yesterday.
MINE, PROCESSING PLANT, TREATMENT BLDGS
$50,000,000 Cochrane Dist ON Prebid
CONDO APARTMENT BLDG, COMMERCIAL OFFICE, RETAIL
$50,000,000 Toronto ON Prebid
EDUCATION BUILDINGS, ADDN ALTS
$40,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Construction Sector Council’s firm-capacity survey to identify challenges
- Pride, sadness as Hogg's Hollow memorial unveiled
- Commemorative quilt gets permanent home
- Getting a lift at iLoft condos in Toronto
- ‘Sandhogs’ who perished had diverse personal stories
- Construction Safety Association of Ontario saluted for pioneering role in provincial health and safety
- Work continues on Mona Lisa Residences in North York, Ontario
- Association of Consulting Engineering Companies campaign targets students
- China to bid on U.S. high-speed rail projects
- Northern Ontario First Nations demand consultation on chromite mining
- Filling labour gap a top priority for incoming Canadian Construction Association chair
- Safety issues raised as Vancouver hires chief electrical inspector
- Buildex Edmonton seminar to examine worksite safety on green building projects
- Canadian Construction Association awards highlight excellence
- Chilliwack Cultural Centre project sets tilt-up concrete record
- Imperial Oil choses Finning International as mining equipment supplier for oilsands project
- BC Hydro awards purchase agreements for 19 clean wind, run-of-river energy projects
- Ledcor continues construction on mixed-use project in Vancouver
- Role of general contractor has evolved over the years
- Alberta Pipe Trades College ready to open the valve on training
- Friction grows between generals and trades during recent downturn
- Green building adding to administrative burden for contractors
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Sub-sector investment spending intentions from Statistics Canada’s latest survey (March 17, 2010)
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- More