Pervious concrete requires careful installation that differs from methods used for conventional concrete, a need addressed by a one-day Ready Mixed Concrete Association of Ontario training course.
Kortright job will put pervious concrete to the test
Green-friendly benefit targeted in parking lot job
The Kortright Centre for Conservation in Kleinburg is testing the waters, so to speak, with the installation of 12,000 square feet of pervious concrete for its parking lot this spring.
The porous concrete is seen as green-friendly because it allows storm water to drain through it to the soil below, rather than diverting it into the region’s underground stormwater infrastructure. The concrete contract will be done by Lafarge Construction, starting in April or May, depending on weather.
While pervious concrete has been around for the better part of a decade, it is making a play for bigger piece of the market these days because of the growing emphasis on sustainable design and construction.
Along with its draining abilities, another benefit is that it contributes to better air quality by lowering atmospheric heating through its light colour and low density. That decreases the heat island effect (temperature increases of up to 4 Celsius) created by dark pavement (asphalt), explains John Hull, president of the Ready Mixed Concrete Association of Ontario.
But a pervious concrete parking lot is not just green, it is cheap. Or at least it can be, when compared to the price of an asphalt parking lot and its associated stormwater management costs, says Hull. Furthermore, land ordinarily devoted to costly stormwater management practices with an asphalt lot can be developed or preserved when pervious concrete is selected instead, says Hull.
Because pervious concrete doesn’t rely on stormwater infrastructure, it is well suited to retail malls such as big box centres and residential subdivisions, he says, adding the porous surface might get the OK in some areas of municipalities where asphalt parking lots are no longer permitted.
Pervious concrete is comprised of coarse aggregate, cement materials and water. Its porous structure (15-30 percent voids in hardened state) is a result of its low sand content, says Hull, noting flow rates of at least 200 litres of water per minute pass through each square metre of pervious pavement when it is properly installed.
Typically, a parking lot consists of a 150-millimetre thick topping of pervious material over a 300-millimetre base of open graded granular.
The base acts as a reservoir for storm water which is gradually filtered down into ground soil, helping to nourish the surrounding green landscape and replenish aquifers.
While installation is not difficult, placing and finishing methods are not like conventional designs.
The low-sump product doesn’t require concrete pumps, drainage pipes or skimmers for grading, says Hull. “It is put down flat with an asphalt spreader or fixed forms and a roller screed is used to place it.”
Because curing starts immediately a polyethylene sheet is placed over the surface immediately.
Hull says while it is straightforward to install, if improperly placed serious problems can result. In one instance, an inexperienced contractor overly compacted it, minimizing its draining ability.
To prevent installation mistakes the RMCAO offers a one-day training course (registered to the National Ready Mix Concrete Association in the U.S.) for contractors. To date, about 150 people have completed the course.
| MOST POPULAR STORIES |
- Steel hurdles for Aga Khan Museum build
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Toronto Construction Association presents ‘Best of the Best’ awards
- Bidding closes for Toronto 2015 Pan Am games venues
- Steel key for CF-5 fighter jet monument at Toronto defence facility
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 288 projects with a total value of $2,181,603,356 that Reed Construction Data Building Reports reported on Friday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$107,557,000 Burlington ON Tenders
CONDOMINIUM APARTMENT BUILDING
$31,300,000 Toronto ON Prebid
| CURRENT STORIES |
- Steel truss system helps reduce construction cost of Toronto apartment building
- Ontario College of Trades will drive up infrastructure costs: Conservative leader Tim Hudak
- Procurement needs to be fair, open and transparent
- Losing bidder bridles at Pan Am Games park selection, Equine Canada “thrilled”
- Armstrong extended at Ontario College of Trades
- CVTech secures Hydro Quebec construction, maintenance work
- Toronto council votes in favour of light rail transit
- Ottawa City Council approves affordable housing capital projects
- Pre-cast concrete segment falls into river after gantry crane collapses
- Alberta throne speech hints at development plan
- Union claims construction oversight needed at defence department
- Site prep in North Vancouver
- Legislation limiting strikes ruled unconstitutional
- World Plumbing Day garners support from Canadian senator
- PHOTO GALLERY: Merit Alberta open house
- Seeing the sustainable forest for the trees
- Pump Station Upgrades
- Labour federation opposes pipeline
- Site for new correctional facility selected
- Edmonton roofer dies
- Regulators approve oilsands facility expansion
- Highway 3 upgrades
- New chairman named for Alberta Construction Association
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Home starts and job levels diverge in Canada and the U.S. (February 8, 2012)
- Canada’s labour market flat in January but U.S. on a roll (February 3, 2012)
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- More