The technology has improved significantly over the last 10 years, but curtain walls and window walls still have to be carefully designed and thoroughly tested before they’re erected.
“There will always be site specific modifications and challenges, but the major design decisions shouldn’t be made by the guys in the field, says Steven Murray, senior project manager with Morrison Hershfield Limited.
A building envelope specialist, Murray he presented an overview of the sector at last fall’s Construct Canada show. While touching on subjects such as water management, thermal performance, design options and durability, the main thrust of his talk was that new technology doesn’t rule out the need for careful planning and design.
Some of the crucial decisions which must be evaluated in the design review include the impact on the overall building design, the functionality of the curtain and window walls, security measures, energy efficiency and material options, he said.
As part of the drawing review, designers should carefully look for junctions and movement joints and consider the impact on the installation on adjacent trades.
“Who makes what connections? If it (the connection) is not clear, define it. You don’t want the guys in the field making these
Steve Murray
The challenge in the planning and design stage is to co-ordinate the scheduling of various trades, with the aim of defining their different responsibilities and where possible minimizing the number of trades involved in the installation, he says.
For LEEDS, its also crucial to review and analyze measures such as glazing, the coating, the fiberglass pressure plates, and energy modeling. Thermal analysis stage is also critical.
The final stage of design and planning, mock up and testing, is an opportunity to refine the wall’s constructability, review geometric conflicts and ensure the function and preserve the appearance of the wall.
“If modifications are necessary, the design has to be modified before production and installation begins,” he said.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Stakeholders react to Ontario College of Trades proposed membership fees
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- Historic Burlington, Ontario railway station to be moved
- Widespread opposition to Ontario College of Trades membership classes
- Safety training today builds safety leaders of the future, says IHSA
- Denis Dixon new Professional Engineers Ontario president
- University of Windsor design competition winners announced
- Construction material costs “took a breather” in April: Associated General Contractors of America
- Almost fit for a King
- Contractors warned about PST transition
- Fort McMurray aggregate producer expands to meet demand
- Another multi-billion dollar LNG terminal proposed for Kitimat
- Best open shop contractors honoured
- Learning to dig safely in B.C.
- Review of Saskatchewan labour laws concerns unions
- Big deal for Ritchie Bros.
- Contracts awarded for 17 Wing in Winnipeg
- Highway 3 improvement contracts awarded
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More