LATEST NEWS
Concrete | Steel | Heavy Equipment | Green Building | Building Envelope | Sewer & Watermain
April 28, 2009
Vancouver ice venue posed unique project challenges
To an experienced builder, constructing your typical arena is generally straightforward. But the new $14 million Trout Lake Ice Arena in east Vancouver is anything but typical.
The 30,000 square-foot arena at John Hendry Park — which will be used as a figure skating practice arena for the 2010 Olympics — was the most challenging project of Russ Hallam’s career.
Hallam was Bird Construction’s site superintendent on the recently completed project. He says assembling and erecting the complex roof frame was one of the most difficult elements of the project. Bird was the project’s general contractor.
It took plenty of planning and 30 hours to erect the massive 210-foot-long arched steel truss that spans the length of the arena, he explains.
The truss actually is made up of three 70-foot sections, each which required crane support during the erection in several locations.
The steel truss was erected by ISM Industrial Steel & Manufacturing with a 270-ton crane and two 50-ton cranes. Glulam beams are anchored perpendicular to either side of the arched truss, giving the roof an appearance from inside the arena of an upside-down boat. The structural consulting engineer on the project was Fast + Epp.
The ribbed structure is clad in metal roof decking. The roof is comprised of a PVC membrane installed by Marine Roofing and an inverted V-rib deck designed to repel rainwater.
Another challenge was constructing the half-metre thick foundation underneath the ice rink. It is composed in part of a one-foot thick base of compacted gravel, topped with a four-inch drainage layer of pea gravel.
A loop of heating tubes (to prevent permafrost extending down from the refrigeration pipes) is buried in a one-foot layer of sand.
Spaced one foot apart, the tubes stretch the length of the rink, terminating at a header trench housing heating and cooling equipment. The tubes are buried in four inches of sand which is topped with rigid insulation between sheets of poly that act as a vapor membrane.
Above the insulation is a series of rebar supports, refrigeration piping, and metal mesh for the concrete. Hallam says to that ensure the ice temperature is constant throughout, every layer below it had to be perfectly level.
If refrigeration pipes were at slightly different depths, the ice surface could develop hard and soft areas.
The concrete slab was installed in a 14-hour continuous pour. To ensure an even and slow cure, the day after the pour the floor was flooded with quarter-inch of water left in place for a week. Edmonton-based Bry Sand Ice Arena installed the floor.
The 100-foot by 200-foot international-sized rink offers seating for 250. After the Olympics, it will be retrofitted to NHL standards of 85-feet by 200-feet. The arena also features a skaters’ lounge, administrative areas and four change rooms built under a green roof.
Most of the arena is a concrete cast-in-place structure. Formwork had to be leakproof because a high-flow self-compacting architectural concrete was specified. Hallam says even a nail-sized-hole would allow the concrete to leak out of the forms in minutes. The concrete pour, done by Syber Concrete Forming Ltd., took three months to complete.
Designed by Walter Francl Architecture Inc., the arena is set on sloping terrain in John Hendry Park.
The interior is swathed in natural light through a band of elevated windows with motorized blinds which automatically shut under direct sunlight conditions to prevent the ice from warming. The project is targeting a LEED Silver certification.
Hallam says as daunting as the project was, Bird Construction managed to bring the job in four months ahead of the original construction schedule, largely because of revisions to the building program before the first shovel hit the ground.
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Caterpillar dispute a factor in CAW-CEP union merger talks
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Future unclear for price of iron ore, scrap steel, rebar
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 333 projects with a total value of $7,273,203,495 that Reed Construction Data Building Reports reported on Thursday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$80,000,000 North York ON Tenders
CONDOMINIUM APARTMENT BUILDING, RETAIL
$75,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Ontario Road Builders’ Association focused on partnerships at convention
- Construction continues on the Regent Park Aquatic Centre in Toronto
- BML Multi Trades president Jim DiNovo takes helm of Hamilton-Halton Construction Association
- Seeing the sustainable forest for the trees
- Steel hurdles for Aga Khan Museum build
- Milton, Ontario council approves velodrome for 2015 Pan Am games
- ASHRAE, International Association of Plumbing and Mechanical Officials plan to cooperate on codes, standards
- MOD Developments 60-storey Massey Tower to include restoration of 1905 Toronto bank
- ERA Architects to conduct study for possible heritage district in Picton, Ontario
- Burlington, Ontario announces preferred hospital redevelopment site
- Bing Thom Architects to design Surrey Performing Arts Centre
- Wind farm contract awarded
- Opposition grows after deal collapses
- $1.8 billion in improvements planned for Vancouver airport
- When low bidders sue over contracts
- North Vancouver condos take shape
- U.S. firms expect fewer layoffs in 2012
- Maple Leaf Gardens time capsule discovered
- A look at Canada's historic concrete ship
- Partnership announced between File Hills Qu'Appelle Tribal Council and Graham Business Trust
- Mike Holmes-designed community in Alberta gets go ahead
- Province of British Columbia contributes cash to green energy projects
- Program for upcoming apprenticeship forum released
- New VRCA chair elected
- Construction union wage index remains the same
- Alberta government orders immediate site remediation
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








