LATEST NEWS
June 10, 2009
Infrastructure
Roadbuilders urge deadline extension for stimulus funding
Weather, regulations barriers to hitting stimulus project deadline
A six-month completion deadline extension for outdoor projects attempting to secure federal stimulus funding would help address weather and regulatory challenges, say local road and sewer building associations.
“The climate realities and the nature of what they wanted for stimulus projects, with core infrastructure and so much in the road right-of-way, will take 2011 out of the equation,” says Frank Zechner, executive director of the Ontario Sewer and Watermain Construction Association.
Some municipal and industry leaders have called for an extension of at least a year to the stimulus funding which comes with a March 31, 2011 project-completion deadline.
In order to qualify for Ottawa’s $4 billion federal stimulus funding, a project must prove it can be completed by then.
Federal infrastructure and transport minister John Baird has said that there will be no extensions.
Zechner says that in most of Canada, road and pipe construction season generally ends by November 30. In places such as Northern Ontario, Quebec, Manitoba and Saskatchewan, it ends much earlier than that.
By the time winter, snow, ice and frost are no longer a factor, for outdoor construction, it will be early April of 2010 with the possible exception of lower Vancouver Island, Windsor and the Niagara peninsula.
Frank Zechner
“That would suggest that outdoor sewer, watermain and road projects that have a March 31, 2011 deadline have to be completed by November 30, 2010,” says Zechner. “What in headlines is a two-year stimulus package therefore becomes a 13 to 14 month stimulus project.”
Municipalities applied for federal stimulus funding by May 1 of this year and they could learn by mid-June whether their specific projects are approved. Even with a four- to six-week fast-track call for tenders by municipalities, followed by an approximate three- to five-week period for contractors to prepare bids, this leaves a bid closing date of late August, Zechner says.
“Bid evaluation and award of the contract then takes us to late September 2009,” he says. “Mobilization by the contractor, requesting and obtaining utility locates, etc. then gets us into October to actually allow shovels to hit the ground.”
Besides weather challenges, the regulatory hurdles which come with projects, once they are approved, will create delays that should be accounted for, says the Ontario Road Builders’ Association (ORBA). The association is already seeing an increase in requirements for certificates of approvals for many types of construction activities. Even a six-month completion deadline extension could help mitigate those delays.
“There will be delays not just due to weather but also delays thanks to the regulatory requirement application period,” notes Karen Renkema, ORBA’s government relations director.
“Whether it is a water-taking permit, or blasting one, any of that can delay a project from six to eight weeks, in some cases — for some of these certificates of approvals; they can wait six to eight months.”
The province should take the opportunity to be innovative, Renkema says. For example, if a project is delayed by five months, because it had to wait that long for a water-taking permit, then that project’s completion deadline should be extended an extra five months.
“The federal and Ontario governments should be taking a good hard look at what projects will be delayed and what will be the delays getting them off the ground,” says Renkema. “Even though they may be shovel-ready for tender does not mean that the certificates of approval have been applied for. None of that has been done until a project is awarded.”
The Residential and Civil Construction Alliance of Ontario (RCCAO) agrees that if regulatory approves take longer than expected, completion deadlines should be extended accordingly. Also, the economic slowdown could last longer than expected.
“We need fixed strategic priorities and not artificial set deadlines, flexible parameters will definitely help,” notes Andy Manahan, RCCAO executive director.
| MOST POPULAR STORIES |
- Steel hurdles for Aga Khan Museum build
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Toronto Construction Association presents ‘Best of the Best’ awards
- Bidding closes for Toronto 2015 Pan Am games venues
- Steel key for CF-5 fighter jet monument at Toronto defence facility
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 288 projects with a total value of $2,181,603,356 that Reed Construction Data Building Reports reported on Friday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$107,557,000 Burlington ON Tenders
CONDOMINIUM APARTMENT BUILDING
$31,300,000 Toronto ON Prebid
| CURRENT STORIES |
- Steel truss system helps reduce construction cost of Toronto apartment building
- Ontario College of Trades will drive up infrastructure costs: Conservative leader Tim Hudak
- Procurement needs to be fair, open and transparent
- Losing bidder bridles at Pan Am Games park selection, Equine Canada “thrilled”
- Armstrong extended at Ontario College of Trades
- CVTech secures Hydro Quebec construction, maintenance work
- Toronto council votes in favour of light rail transit
- Ottawa City Council approves affordable housing capital projects
- Pre-cast concrete segment falls into river after gantry crane collapses
- Alberta throne speech hints at development plan
- Union claims construction oversight needed at defence department
- Site prep in North Vancouver
- Legislation limiting strikes ruled unconstitutional
- World Plumbing Day garners support from Canadian senator
- PHOTO GALLERY: Merit Alberta open house
- Seeing the sustainable forest for the trees
- Pump Station Upgrades
- Labour federation opposes pipeline
- Site for new correctional facility selected
- Edmonton roofer dies
- Regulators approve oilsands facility expansion
- Highway 3 upgrades
- New chairman named for Alberta Construction Association
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Home starts and job levels diverge in Canada and the U.S. (February 8, 2012)
- Canada’s labour market flat in January but U.S. on a roll (February 3, 2012)
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- More








