November 27, 2009
DAVID GREEN
Dust and run-off entering a waterway is a major symptom of construction pollution.
FEATURE | Demolition & environmental engineering
Demand for environmental monitoring on the rise
Construction still sends ‘ridiculous’ amounts of dust as sediment to waterways and ponds
Moving dirt from Point A to Point B has been a staple of construction projects since humans first began to build. Concerns over erosion and whether soil enters sensitive watercourses are a far more recent phenomenon.
Construction projects are increasingly seeking the assistance of environmental monitors to help prevent and mitigate erosion and other environmental problems, says David Green, an aquatic biologist and an expert in environmental monitoring for construction with Ontario-based Natural Resource Solutions Inc.
To counter the issues of run off, in 2006 the Greater Golden Horseshoe Area Conservation Authorities developed The Erosion and Sediment Control Guideline for Urban Construction.
“We were seeing a lot of construction projects going in a bad way,” says Green. “But the document wasn’t a cookbook. It was designed to support everyone in doing a better job. Handling sediment control on a construction site is a very challenging endeavour that requires a lot of creativity. But, despite efforts to control the problem on construction sites, we’re still losing ridiculous amounts of sediment to the water system, both through the movement of water and wind.”
Green notes sediment that enters a watercourse can have more than a temporary environmental impact. Excess sediment continues to move downstream year after year.
“The sediment can stay in the system for hundreds of years,” he says.
“In some cases you could have huge slugs of sediment from a construction site that can deposit mid-channel and create additional erosion on either bank of a watercourse as water is forced to flow around it.”
Traditionally, engineers have handled the job of environmental monitoring, with specialists called in as needed.
Green says that more construction project owners are calling in an environmental monitor earlier in the game more so as the potential for liability increases.
Since 2006, the Ontario Ministry of Transportation has pre-qualified environmental monitors who have expertise in both environmental disciplines and construction contracts.
Green, who is pre-qualified, says understanding construction contracts is often a key factor in determining erosion and sediment control issues.
“I can look at contract documents, then look at the site and tell you the sediment control issues they’ll be up against,” says Green. “In most cases there’s no deliberate effort to overlook the problem. It’s a contractor’s job to bring in a competitive bid, then show the environmental authorities that a project is constructible, but in many cases what might appear reasonable doesn’t work in practice. If a contractor is dewatering a stream area as part of a construction effort, and they want to use the standard approach of employing sandbags as instream plugs to achieve that end, it may appear reasonable to an environmental agency. But if they screen the project through a monitor, it may be noticed that those sandbags are going to be placed on very thick organic material. Recognizing that a good seal on a soft bottom system is extremely difficult, those sand bags may keep sinking and sinking as they compress the underlying layer. The only effective way to control the water may be to drive sheet pile to depth to block the channel.”
Green says that environmental monitors are most effective when called into a project early on, rather than later.
“Something as simple as phasing construction to limit soil exposure can go a long way to help reduce sediment problems,” he says.
| MOST POPULAR STORIES |
- New technology allows concrete to come clean
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Construction moving forward on Ho Chi Minh City tunnel
- Deaths of five immigrant workers changed jobsites forever
- SNC-Lavalin subsidiary Profac under scrutiny over federal contract billing
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 378 projects with a total value of $3,604,490,024 that Reed Construction Data Building Reports reported on yesterday.
$63,800,000 Markham ON Prebid
RESIDENTIAL, RETAIL DEVELOPMENT
$50,000,000 Thorold ON Prebid
$40,000,000 Etobicoke ON Negotiated
| CURRENT STORIES |
- Pride, sadness as Hogg's Hollow memorial unveiled
- Deaths of five immigrant workers changed jobsites forever
- 1960 calamity has parallels to recent swing-stage accident
- ‘Sandhogs’ who perished had diverse personal stories
- British Columbia open shop association takes issue with Burnaby’s ‘fair wage’ policy
- Pursuit of LEED could result in professional negligence, insurance executive warns
- Ontario economic growth expected to beat national average
- Venues decommissioned in Olympic afterglow
- Canadian Construction Association chair bids farewell
- Hogg’s Hollow tragedy changed Ontario’s construction industry
- Wood being considered as preferred building material for federal projects
- ‘Quality product cannot come from cutting corners on safety’
- Grizzly Oil Sands seeks approval for project near Fort McMurray
- Search continues for sustainable architecture
- Seven British Columbia communities sign Wood First agreements
- U.S. construction employment declines in January
- Ottawa unveils plan to cut red tape
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Sub-sector investment spending intentions from Statistics Canada’s latest survey (March 17, 2010)
- A dozen incredible measurement sets on Canada’s changing ethnic mix (March 9, 2010)
- How fragile is recovery around the world? (March 3, 2010)
- More







