November 27, 2009
HIGHWAY CONSTRUCTION INSPECTION
With the QEW shut down, six machines completed the demolition in hours.
FEATURE | Demolition & environmental engineering
Demolition of Martindale Bridge takes hours, not days
ST. CATHARINES, Ont.
In the brave, new world of highway bridge demolition, projects are scheduled over hours, not days.
The Martindale Bridge crossing the Queen Elizabeth Way (QEW) near St. Catharines, Ont. was no exception.
“We usually set some limits and allow contractors a specific number of hours to close the highway and get the work done,” says Ministry of Transportation spokesman Will Mackenzie. “In this case, we were scheduling 10 hours for demolition because of the wideness of the bridge.”
The overpass, constructed in 1939, once supported an intra-urban streetcar line that had long since gone out of service. The additional lane, running alongside the vehicle lane, was eventually devoted strictly to pedestrian and bicycle traffic.
“Because of that feature it was a unique bridge, but it didn’t have any particular historical significance,” says Mackenzie. “After the streetcar line was taken out, the bridge still had that part of the deck.
“Today they would use continuous welded rail, but that wasn’t the case in the 1940s. Most of that type of rail bridge used what was essentially a viaduct filled with a gravel ballast and the track sections were laid on top of that. It allowed for a smoother track and was also easier for railway maintenance.”
The bridge was demolished to be replaced by a new span as part of a $183-million upgrade contract awarded to the Dufferin Construction Company to widen the QEW. The contract represents the last remaining section between Toronto and Niagara Falls that has not been widened to six lanes.
“There simply wasn’t enough room to widen the highway underneath the bridge,” says Mackenzie.
“Originally, the contractor came to us with a plan to detour traffic around the abutment, but later they came to us and said they could do it faster and cheaper if we could close the highway for one night.”
A new single-span four-lane underpass structure was already under construction and ready to accept traffic as the old bridge was being demolished.
The QEW was closed at midnight on Saturday, October 16th between Highway 406 and Ontario Street with Niagara-bound QEW traffic diverted to Highway 406 and Toronto-bound travelers diverted to Thorold Stone Road.
“The standard procedure is to begin by laying a foot-and-a-half to two feet of gravel on the highway to protect the existing road surface underneath from falling concrete and debris,” says Mackenzie.
Tonnes of cushioning material were laid down in the initial minutes of demolition. The contractor then sent in six excavators to attack the bridge simultaneously, as concrete was hammered to rubble and hydraulic cutters sheared steel rebar. Backup units cleared away debris as the excavators progressed. In a few hours, the road was swept clean.
“The site was cleaned up and traffic resumed along the QEW at 10:00 a.m. on Sunday as scheduled,” said Mackenzie.
| MOST POPULAR STORIES |
- Steel hurdles for Aga Khan Museum build
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Toronto Construction Association presents ‘Best of the Best’ awards
- Bidding closes for Toronto 2015 Pan Am games venues
- Steel key for CF-5 fighter jet monument at Toronto defence facility
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $1,890,889,993 that Reed Construction Data Building Reports reported on Thursday.
$65,000,000 Toronto ON Negotiated
RETIREMENT RESIDENCE, COMMUNITY CENTRE
$45,500,000 Toronto ON Negotiated
$40,000,000 Brampton ON Prebid
| CURRENT STORIES |
- Steel truss system helps reduce construction cost of Toronto apartment building
- Ontario College of Trades will drive up infrastructure costs: Conservative leader Tim Hudak
- Procurement needs to be fair, open and transparent
- Losing bidder bridles at Pan Am Games park selection, Equine Canada “thrilled”
- Armstrong extended at Ontario College of Trades
- CVTech secures Hydro Quebec construction, maintenance work
- Toronto council votes in favour of light rail transit
- Ottawa City Council approves affordable housing capital projects
- Pre-cast concrete segment falls into river after gantry crane collapses
- Alberta throne speech hints at development plan
- Union claims construction oversight needed at defence department
- Site prep in North Vancouver
- Legislation limiting strikes ruled unconstitutional
- World Plumbing Day garners support from Canadian senator
- PHOTO GALLERY: Merit Alberta open house
- Seeing the sustainable forest for the trees
- Pump Station Upgrades
- Labour federation opposes pipeline
- Site for new correctional facility selected
- Edmonton roofer dies
- Regulators approve oilsands facility expansion
- Highway 3 upgrades
- New chairman named for Alberta Construction Association
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Home starts and job levels diverge in Canada and the U.S. (February 8, 2012)
- Canada’s labour market flat in January but U.S. on a roll (February 3, 2012)
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- More








