One-third of Ontario’s bridges in critical need of repair: auditor general
One-third of Ontario’s bridges deemed to be in critical need of repair have no repair plans set for over the next year, the province’s auditor general finds in his latest audit.
Auditor General Jim McCarter states in his 2009 annual report that some Ontario bridges are in poor condition and the province is taking too long to make repairs.
"We found that the Ministry of Transportation (MTO) had no plans to make repairs within the coming year to the more than one-third of the 180 provincial bridges identified, by its own inspectors, as being in critical need of repair within the year," McCarter said in a statement.
There are about 14,800 bridges in Ontario and 2,800 of them are under provincial ownership.
Municipalities own the remaining 12,000 and are responsible for their maintenance.
However, the McCarter report noted that MTO "lacked comprehensive information" about the condition of bridges owned by municipalities.
Among the report’s findings concerning provincially owned bridges:
- In a 2006 training workshop, ministry inspectors and external consultants both commented that their work was challenged by not being able to gain adequate access to perform thorough, close-up inspections of large bridges.
This issue is particularly serious in the Greater Toronto Area, where there are over 660 bridges on the 400 series of highways and some of them span up to 16 lanes of traffic. Half of these bridges are 40 years or older.
- MTO’s own inspection manual states a typical bridge examination should take at least two to three hours.
However, the audit found that inspectors often conducted five or more bridge inspections a day and 10 or more bridges were inspected in one day, by a single inspector, on 36 different occasions between 2006 and 2008, raising doubts as to the thoroughness of these inspections.
- MTO’s Bridge Management System did not have information on the rehabilitation history for almost one-third of the bridges that were 40 years old or older.
MTO confirmed that rehabilitation work had been done on some of these bridges in the last 12 years and detailed information was available in paper files or on the local database, yet none of this work had been entered into the system.
- The auditor general found that in over 60 per cent of contracts it reviewed for design services and construction contract oversight, MTO’s estimate "differed significantly" from that of the selected bidder.
In many cases, the winning bid was 50 per cent higher than the Ministry’s own initial estimate.
Contract addenda were found in about 75 per cent of the contracts reviewed for the report and in half of these, the added costs amounted to more than 50 per cent of the original contract price.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Stakeholders react to Ontario College of Trades proposed membership fees
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- Historic Burlington, Ontario railway station to be moved
- Widespread opposition to Ontario College of Trades membership classes
- Safety training today builds safety leaders of the future, says IHSA
- Denis Dixon new Professional Engineers Ontario president
- University of Windsor design competition winners announced
- Construction material costs “took a breather” in April: Associated General Contractors of America
- Almost fit for a King
- Contractors warned about PST transition
- Fort McMurray aggregate producer expands to meet demand
- Another multi-billion dollar LNG terminal proposed for Kitimat
- Best open shop contractors honoured
- Learning to dig safely in B.C.
- Review of Saskatchewan labour laws concerns unions
- Big deal for Ritchie Bros.
- Contracts awarded for 17 Wing in Winnipeg
- Highway 3 improvement contracts awarded
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More