Manitoba fast-tracks Pierre Delorme bridge repair plan
The province of Manitoba is fast-tracking plans to repair and reopen a bridge south of Winnipeg that partially collapsed last summer due to riverbank instability.
“We are going to repair the bridge and replace the sections that were demolished,” said Ron Weatherburn, executive director with the Manitoba Infrastructure and Transportation.
“We demolished two piers and three spans. We have issued a tender for the replacement of two piers. Next, we will tender for spans to be replaced and have the bridge up and running by November 2010.”
The Pierre Delorme Bridge in St. Adolphe was closed Aug. 21 after an inspection revealed one of its massive supporting piers had shifted, causing severe structural instability.
“There was a riverbank issue, so we have done a fair amount of work already to stabilize the bank,” said Weatherburn.
“We will also be doing more stabilization work.”
It is believed the pier started moving shortly after the spring flood, when the Red River receded.
The pier continued to sink and dropped more than three metres in 24 hours, which caused the bridge deck to buckle.
Two conventional excavators with jack hammers were used to remove the damaged piers and sections of the bridge. At that time, it wasn’t known if the bridge could be salvaged. However, crews still worked to save as much of the remaining structure as possible.
An assessment determined that the bridge didn’t need to be reconstructed, as well as what piers and deck span sections needed to be replaced.
Weatherburn said the tender for the first phase is out and is due to close in January.
The contractor will start work immediately on the first phase, which involves the construction of two piers.
“The second phase is for the construction of the spans and the deck,” he said. “In the fast track process, we are tendering the first phase, while the second phase is still being designed. We want this up as soon as possible.”
Weatherburn said it is still not known how much the work will cost, but, he said, it will be in the millions.
As a result of the collapse, the bridge was closed. Motorists, boaters and the general public are not allowed to travel on, walk on or boat under the bridge.
Town residents and other motorists have been forced to use an alternate route which takes them dozens of kilometres out of their way.
Given this situation, officials with the Rural Municipality of Ritchot asked the provincial government to build an ice road to speed up access to the community in the winter.
At the site of the bridge, there was a winter crossing in the 1970’s and some dirt sections of the historical ice road infrastructure are still in place.
“The community asked for an ice bridge, but there are safety issues and the province decided not to proceed,” said Weatherburn.
These safety concerns were related to changing river levels, which cause ice near the shoreline to weaken or open altogether during the winter.
Another possible reason for the rejection of the proposal is a general movement away from ice roads and limited infrastructure resources.
The Pierre Delorme Bridge carries major traffic across the Red River and connects two major north-south routes.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Stakeholders react to Ontario College of Trades proposed membership fees
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- Historic Burlington, Ontario railway station to be moved
- Widespread opposition to Ontario College of Trades membership classes
- Safety training today builds safety leaders of the future, says IHSA
- Denis Dixon new Professional Engineers Ontario president
- University of Windsor design competition winners announced
- Construction material costs “took a breather” in April: Associated General Contractors of America
- Almost fit for a King
- Contractors warned about PST transition
- Fort McMurray aggregate producer expands to meet demand
- Another multi-billion dollar LNG terminal proposed for Kitimat
- Best open shop contractors honoured
- Learning to dig safely in B.C.
- Review of Saskatchewan labour laws concerns unions
- Big deal for Ritchie Bros.
- Contracts awarded for 17 Wing in Winnipeg
- Highway 3 improvement contracts awarded
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More