January 25, 2010
Seymour-Capilano filtration plant nearly complete in North Vancouver
VANCOUVER
The completion of construction deficiencies continues on the Seymour-Capilano filtration plant, as Metro Vancouver prepares the facility for operation.
“We are slowly introducing more and more water and testing the system,” said Glenn Bohn, communications specialist with Metro Vancouver.
“The commissioning of the Seymour-Capilano treatment plant is well underway. We began deliveries of filtered Seymour water from the plant in December. The commissioning is being ramped up in the coming weeks.”
The Seymour and Capilano watersheds supply up to 70 per cent of the Lower Mainland’s drinking water.
The Seymour-Capilano filtration plant, which is the largest facility of its kind in Canada, will filter up to 1.8 billion litres of water per day.
“Seymour source water is going through the Seymour-Capilano filtration plant and 65 per cent of the water from the Seymour River is being filtered through the plant,” said Bohn.
A quarterly report submitted to the Water Committee in November 2009, said NAC Constructors were busy completing construction deficiencies throughout the plant.
In September the plant was 97 per cent complete and Metro Vancouver was planning for transfer of site safety responsibilities from the prime contractor to Metro Vancouver.
“All of the major construction contracts are nearing completion, except for the twin tunnels,” said report author Mark Ferguson, water and wastewater treatment division manager.
“As of the end of September 2009, twin tunnels completion is 55 per cent. The balance of the project is at 97 per cent overall completion. Filtration of Seymour and Capilano source waters is scheduled for late 2009 and mid-2013, respectively.”
In order to treat water from both sources at one plant, water has to be moved between Seymour and Capilano through underground twin tunnels.
Bilfinger-Berger Canada (BBC) Inc. was hired in 2004 by Metro Vancouver to construct the twin tunnels with a combined length of 14.2 km. Work on the project was suspended by BBC in January 2008 due to concerns about the safety of underground workers.
As a result of this action, Metro Vancouver terminated BBC’s right to perform further work on the project on May 26, 2008.
In April 2009, Metro Vancouver finalized negotiations and awarded a new contract for completion of the twin tunnels to the Seymour-Cap Partnership, which is made up of Frontier-Kemper, J.F.Shea and Aecon.
“Tunnelling in the treated water tunnel (TWT) and raw water tunnel (RWT) resumed in mid July and late August, respectively,” said Ferguson. “To the end of September, the treated water and raw water tunnels were at 4.1 km and 4.2 km respectively (58 per cent of tunnels boring). This represents advances of 300m in the TWT and 65m in the RWT since the resumption of the work.”
Northwest Pipe in California is manufacturing welded steel liner pipe for the tunnels, including lining and coating work.
This work is about 75 per cent complete.
Delivery of the liner pipe to Metro Vancouver’s temporary storage site adjacent to the Annacis Island Wastewater Treatment Plant continues with 61 per cent of pipe received.
Ferguson said overall completion of the tunnels was 55 per cent at the end of September.
Projected substantial completion is spring 2013 with the tunnels in service by mid-2013.
Filtration improves drinking water quality by removing micro-organisms, organics, silts and clays caused by heavy rainfall, and reduces the amount of chlorine required to maintain water quality.
The water will also be treated to reduce corrosion in pipes and the staining of plumbing fixtures.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Stakeholders react to Ontario College of Trades proposed membership fees
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- Historic Burlington, Ontario railway station to be moved
- Widespread opposition to Ontario College of Trades membership classes
- Safety training today builds safety leaders of the future, says IHSA
- Denis Dixon new Professional Engineers Ontario president
- University of Windsor design competition winners announced
- Construction material costs “took a breather” in April: Associated General Contractors of America
- Almost fit for a King
- Contractors warned about PST transition
- Fort McMurray aggregate producer expands to meet demand
- Another multi-billion dollar LNG terminal proposed for Kitimat
- Best open shop contractors honoured
- Learning to dig safely in B.C.
- Review of Saskatchewan labour laws concerns unions
- Big deal for Ritchie Bros.
- Contracts awarded for 17 Wing in Winnipeg
- Highway 3 improvement contracts awarded
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More