Project progress

Getting a lift at iLoft condos in Toronto

WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

A panel gets lifted into place at the iLoft condominiums on Legion Road North in Toronto. Toddglen Construction Co. Ltd. is construction manager of the 28-storey, 230-unit project, which includes an exercise room, pool/sauna, squash courts and a party room.

The iLoft project was designed by Atkins Architects Inc.

Consultants are Y & V Engineering Ltd. (structural) and CBM Engineering Group (mechanical/electrical).

Subtrades include: Costa Earthmoving Inc. (excavation); Deep Foundations Contractors Inc. (shoring/caissons); High-View Forming (1995) Inc.; Dufferin Concrete; Salit Steel (Niagara) Ltd. (rebar); Marli Mechanical; Titan Mechanical (ventilation); Zerem Electrical Services; and Allan Windows Ltd.

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 282 projects with a total value of $3,305,741,968 that Reed Construction Data Building Reports reported on yesterday.

AIR-RAIL LINK, STATIONS, ROADWORK, BRIDGE

$515,000,000 Province of Ontario ON Negotiated

OFFICE BLDG, GARAGE ALTS

$100,000,000 Toronto ON Negotiated

CONDOMINIUM APARTMENT BUILDING

$31,000,000 North York ON Prebid

Daily Top 10

CURRENT STORIES
ALEX’S ECONOMICS BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

TODAY’S TOP JOBS

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design