LATEST NEWS
Green Building | Roadbuilding | O H & S | Heavy Equipment | Trade Contracting
June 25, 2010
FLYNN CANADA
Workers for Flynn Canada’s green roof division work on an installation above Toronto’s Nathan Phillips Square.
Building Toronto city hall green roof posed host of challenges
Construction crews building a living roof atop the second-storey podium at Nathan Phillips Square could be forgiven for thinking they were working inside a library. The $2.3 million living roof will stand as one of the city’s quietest projects — at least when politicians and administrative staff didn’t want to be disturbed.
“It wasn’t easy working in a place that’s so public,” says Mary Tremain, a partner with Plant Architect, which designed the space through a joint venture with Shore Tilbe Irwin and Partners (since merged to form Shore Tilbe Perkins+Will).
If it seems like there’s been a greenery up there for at close to a decade, that’s not far off the mark. In fact, municipal green roof proponents had used the space as a test bed for several years.
The real thing — 37,000 square feet of greenery, paved walkways and eco-friendly LED lighting — opened late last month and ranks as the largest living roof in Toronto.
Plant Architect did the planting, lighting, paving and other surface finishes, as well as the design, while Shore Tilbe Irwin oversaw work on the membrane, flashing, insulation and electrical.
Tremain says workers were subject to time restrictions because city hall and the square stayed open.
“There were council sessions going on sometimes, which meant construction stopping and starting and working around scheduled events organized on the square,” Tremain says.
Noise and related restrictions proved challenging in terms of scheduling the work, Tremain says.
And, because City Hall is both a modern building and a heritage site, aesthetic and historic needs raised technical challenges.
Shortly into the project, crews discovered the existing roof was built without a slope, contrary to information designers had been provided.
This led to complications, including drainage.
FLYNN CANADA
An overhead view of the green roof at Toronto City Hall.
“Our construction documents were drawn assuming a slope,” Tremain says, explaining that it turned out the slope was removed during a previous renovation.
“We had to redesign the insulation thickness, and that meant the whole sandwich (membrane, insulation and high-performance bedding) that we ended up putting on the roof brought the level of the paving up higher.”
This became a building code issue, and the team had to heighten an existing guardrail, built around the podium perimeter when regulations were more lax.
That, in turn, had heritage and cost implications, Tremain says. “It was kind of snowball effect.”
Gardens in the Sky, a unit of Flynn Canada that builds living roofs, did much of the installation work. Manager Terry McGlade says the roof’s large size and the fact that adjacent areas remained operative made it tough to co-ordinate the various activities.
“It took 44 days just to get the plants up there. Let alone taking down the old interlocking stone and insulation and bringing all the new materials up there. It was a huge mobilization.”
McGlade says existing buildings are generally more difficult than new sites because they’re often active. “People were working in the building, we had to close off a street to get materials up there, and we could only use the square when people weren’t there.”
A related challenge was public safety. Because the podium wasn’t sealed off, crews had to watch out for curiosity seekers venturing up the outdoor ramp from the square below.
“We had to protect people from our overhead craning and we had to build a scaffold roof to protect people going into the building on the back side,” McGlade says.
Crews often loaded and unloaded at 5 a.m., when the building was easily accessible and popular thoroughfares such as Bay Street were relatively empty.
As is often the case with green roofs, weather proved a powerful factor. While the winter turned out to be unusually mild, the podium seemed under continuous wind attack.
“When the building was built there weren’t that many tall high-rises around, but now there are,” McGlade says. “All the work we did one day would get moved and we’d have to go back and replace it. This happened a few times.”
Crews weighted down a particularly vulnerable drainage board above the roof membrane, but the constant jockeying of weighted materials took time.
“That’s the nature of construction,” McGlade philosophizes. “Nothing ever works as easily as you want it to.”
The project is vying for LEED Gold certification through the Canada Green Building Council. Green attributes include the recycling of old materials, including interlocking stone and standard high-density blue styrofoam insulation.
“The plants are grown locally just outside London, so we should easily achieve LEED Gold,” McGlade says.
With the green roof completed, planners and crews can turn to the project’s second phase.
The square’s revitalization plans include a permanent stage, a two-level restaurant, a landscaped perimeter, an information kiosk and a new skating rink. The overall cost, including the green roof, is projected to be $42.7 million, with completion scheduled for 2012.
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Caterpillar dispute a factor in CAW-CEP union merger talks
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Future unclear for price of iron ore, scrap steel, rebar
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 333 projects with a total value of $7,273,203,495 that Reed Construction Data Building Reports reported on Thursday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$80,000,000 North York ON Tenders
CONDOMINIUM APARTMENT BUILDING, RETAIL
$75,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Ontario Road Builders’ Association focused on partnerships at convention
- Construction continues on the Regent Park Aquatic Centre in Toronto
- BML Multi Trades president Jim DiNovo takes helm of Hamilton-Halton Construction Association
- Seeing the sustainable forest for the trees
- Steel hurdles for Aga Khan Museum build
- Milton, Ontario council approves velodrome for 2015 Pan Am games
- ASHRAE, International Association of Plumbing and Mechanical Officials plan to cooperate on codes, standards
- MOD Developments 60-storey Massey Tower to include restoration of 1905 Toronto bank
- ERA Architects to conduct study for possible heritage district in Picton, Ontario
- Burlington, Ontario announces preferred hospital redevelopment site
- Bing Thom Architects to design Surrey Performing Arts Centre
- Wind farm contract awarded
- Opposition grows after deal collapses
- $1.8 billion in improvements planned for Vancouver airport
- When low bidders sue over contracts
- North Vancouver condos take shape
- U.S. firms expect fewer layoffs in 2012
- Maple Leaf Gardens time capsule discovered
- A look at Canada's historic concrete ship
- Partnership announced between File Hills Qu'Appelle Tribal Council and Graham Business Trust
- Mike Holmes-designed community in Alberta gets go ahead
- Province of British Columbia contributes cash to green energy projects
- Program for upcoming apprenticeship forum released
- New VRCA chair elected
- Construction union wage index remains the same
- Alberta government orders immediate site remediation
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








