July 30, 2010
FEATURE | Site services
ROBERT B SOMERVILLE
Directional drilling helps keep community relations on a good footing because it is less disruptive.
Directional drilling less disruptive for locals
While Canada offers plenty of open spaces as potential wind farm sites, there’s a catch.
To make them viable they have to be located near existing transmission lines.
The Talbot Wind Energy Project being constructed along Lake Erie in the Municipality of Chatham-Kent near Ridgetown fits the bill.
To assure local residents the construction and operation of the wind farm would have as little effect as possible on both the environment and the site, developer Res Canada chose directional drilling to lay as much of the electrical infrastructure as possible.
That’s one of the lessons learned in previous wind farm projects where local opposition was galvanized against invasive construction methods.
“In some wind farms, they put the electrical infrastructure overhead on poles along the road,” says Abe Dyck, manager, Contracts and Business Development, with the Robert B. Somerville Co. Limited. “Where they couldn’t get agreement with the local utility to use existing hydro poles, they had to erect a second set of poles.”
The company has been working since May to install 70-kilometres of cable consisting of three primary, one fibre and one ground cable in a polyethylene conduit about eight inches in diameter.
Dyck says a considerable portion of the infrastructure is being installed using simple open cut technology where soil beds for conduit are merely compacted and backfilled.
“The directional drilling is used in front of people’s properties, or in front of businesses where the owner doesn’t want to see things disrupted,” says Dyck. “The municipality also had century-old trees along the roadways they didn’t want to see harmed.”
Installation is further constricted by existing infrastructure, including utility poles and a patchwork of public and private property access requirements. Archaeological studies also identified areas of historic interest that were to be left undisturbed.
Directional drilling lengths have ranged from as little as 20 metres to as many as 500 metres, using multiple horizontal directional drilling rigs including units manufactured by American Auger and Vermeer directional drills.
Crews dig a pilot hole, pushing a bore head connected to a hollow pipe into the ground. As each joint of drill pipe enters the ground, a new one is added. A jet of high-pressure drilling fluid, most commonly a mixture of bentonite clay and water, provides the majority of the drilling action, though the units can also take advantage of a rotating drill bit. The fluid performs double duty, also cooling and lubricating the pipe.
During the drilling process, crew members use a locating machine to determine the exact position of the drill head, which reports back on its angle of access, depth, rotation, direction and temperature. That data is fed back to the unit, which self-adjusts to drill according to plan. When the drill head emerges on the other side, the bit is removed and replaced by a reamer which is pulled back while rotating the drill pipe.
Once the diameter had been achieved, the conduit pipe is attached to the reamer and pulled back through the hole, while drilling fluid is pumped in to fill any voids between pipe and soil.
“On jobs in urban centres such as Toronto, the Robert B. Somerville Co. typically relies on directional drilling as its primary approach. “For a rural area, this turned out to be a large directional drilling project, with more crossings than we anticipated,” says Dyck.
Occasionally, the drilling machines dig up a surprise, such as the day at Ripley Wind Farm near Kincardine when crews found artillery shells buried beneath the ground.
“The site was near Camp Borden where they used these areas for practice rounds,” says Dyck. “We brought in an artillery expert who proved they weren’t live ammunition.”
Work on the underground collection system at Talbot should be completed in October.
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Caterpillar dispute a factor in CAW-CEP union merger talks
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Future unclear for price of iron ore, scrap steel, rebar
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 333 projects with a total value of $7,273,203,495 that Reed Construction Data Building Reports reported on Thursday.
STADIUM, BERMS, PARKING GARAGE, SITE WORKS
$129,300,000 Ottawa ON Tenders
$80,000,000 North York ON Tenders
CONDOMINIUM APARTMENT BUILDING, RETAIL
$75,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Ontario Road Builders’ Association focused on partnerships at convention
- Construction continues on the Regent Park Aquatic Centre in Toronto
- BML Multi Trades president Jim DiNovo takes helm of Hamilton-Halton Construction Association
- Seeing the sustainable forest for the trees
- Steel hurdles for Aga Khan Museum build
- Milton, Ontario council approves velodrome for 2015 Pan Am games
- ASHRAE, International Association of Plumbing and Mechanical Officials plan to cooperate on codes, standards
- MOD Developments 60-storey Massey Tower to include restoration of 1905 Toronto bank
- ERA Architects to conduct study for possible heritage district in Picton, Ontario
- Burlington, Ontario announces preferred hospital redevelopment site
- Bing Thom Architects to design Surrey Performing Arts Centre
- Wind farm contract awarded
- Opposition grows after deal collapses
- $1.8 billion in improvements planned for Vancouver airport
- When low bidders sue over contracts
- North Vancouver condos take shape
- U.S. firms expect fewer layoffs in 2012
- Maple Leaf Gardens time capsule discovered
- A look at Canada's historic concrete ship
- Partnership announced between File Hills Qu'Appelle Tribal Council and Graham Business Trust
- Mike Holmes-designed community in Alberta gets go ahead
- Province of British Columbia contributes cash to green energy projects
- Program for upcoming apprenticeship forum released
- New VRCA chair elected
- Construction union wage index remains the same
- Alberta government orders immediate site remediation
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








