FEATURE | Roadbuilding
MTO likes seven-year pavement warranty program
The Ministry of Transportation Ontario (MTO), says its seven-year pavement warranty program — the only program of its kind in North America — will provide an ongoing model for future paving contracts.
The warranty program has undergone a five-year trial phase and combines design-build contracting and multi-year warranties on hot mix paving.
Under the program, MTO does not vet the design of the pavement, but allows contractors to bid on the pavement portion, taking responsibility for pavement design, materials and construction.
The first two projects under the program were awarded in 2006: Highway 94 near North Bay and Highway 23 near Harriston.
Others followed: Highway 132 near Renfrew, Highway 118 near Bancroft, Highway 144 near Timmins, Highway 11 near North Bay and Highway 28 near Peterborough.
The province tested various warranty lengths in order to balance the needs of the province with the abilities and interests of contractors, says Gary Todd, manager, design and contract standards office, MTO.
“In the mid-1990s we tested three- and five-year warranties under a few trials, and essentially the products we got were acceptable,” he says. “But the time period wasn’t really long enough for the pavement to show any defects — after three years any pavement will probably look good. If we went a lot longer, we realized we would be discouraging bidders because that extended period represents a time beyond which the paver could accurately predict the road’s condition.”
Extended warranties had not been applied to contracts for a number of years until the idea was revived in 2004 as part of MTO’s continuous improvement program.
“Seven years seemed to be a good balance between MTO’s interests and the contractors’ interests without discouraging bids,” says Todd. “We have various deterioration curves for various surfaces, but if the contractor can get the road to last seven years to warranty specifications, it’s likely the road will make it all the way to 18 or 20 years.”
He says the current model holds the paving contractor responsible for the design and thickness of the pavement structure, the grade of the pavement and any quality control testing.
“If we need to replace a culvert, for example, we simply set a target for smoothness over the culvert instead of specifying everything about that culvert,” he says. “MTO would continue to specify that the road needs to be capable of carrying a specific load, meet performance criteria for smoothness and skid resistance and use specific aggregate sources for premium mixes.”
Contractors simply bid on how much it will cost to build a stretch of road within those parameters with an effective life of 18 to 20 years. The contract is then awarded to the lowest bid, he said.
“Essentially, we’ve learned some lessons going along through this process with respect to being clear in the specifications,” says Todd.
Through the life of the road projects, 500-metre segments of the pavement are tested for smoothness, pavement friction, and signs of distress, including wheel track rutting, coarse aggregate loss, rippling, shoving, flushing and pavement cracking.
To date, all but one of the projects has produced pavement designs as good as or stronger than MTO specifications and only one project to date has experienced any performance issues.
Todd says contractors have responded well to seven-year warranty bids, with at least three bidders per project.
He notes, however, that MTO expects bids to become more competitive as contractors gain more experience with the system and learn to place a more exact value on the extended risks associated with the project warranties.
MTO has also hosted presentations on pavement distress evaluation to help contractors understand the way that pavements will be evaluated under the seven-year warranties.
“We have pavement management histories on most sections of our highways, so we’ve invited contractors to ask for performance information on any of the contracts they’ve worked on,” Todd says.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Widespread opposition to Ontario College of Trades membership classes
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- Ontario General Contractors Association launches letter writing campaign about College of Trades
- Aspen Ridge continues work on Scenic on Eglinton condos in Toronto
- Construction to start soon on Mission, British Columbia health centres
- Why re-tendering construction contracts after cancelling requests for proposals is fraught with risk
- Teamsters union aims to organizes Windsor Essex Parkway construction dump truck drivers
- Canada’s trade surplus in March increased but remained negligible
- Historic York House in Fredericton, New Brunswick sold to ADI Capital
- Painting and sand blasting firm fined $70,000 in connection with workplace injury in Hamilton, Ontario
- Nine nabbed in Quebec corruption bust
- Canada Lithium signs MOU with First Nations
- Almost fit for a King
- Contractors warned about PST transition
- Fort McMurray aggregate producer expands to meet demand
- Another multi-billion dollar LNG terminal proposed for Kitimat
- Best open shop contractors honoured
- Learning to dig safely in B.C.
- Review of Saskatchewan labour laws concerns unions
- Big deal for Ritchie Bros.
- Contracts awarded for 17 Wing in Winnipeg
- Highway 3 improvement contracts awarded
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More