June 24, 2011
DAN O’REILLY
Demolition of the old chlorine treatment plant by Quantum Murray Demolition began in April.
FEATURE | Sewer and Watermain/Water & Wastewater
How the Lakeview Water Treatment Plant in Mississauga, Ontario will save space
A three-year $106-million project that will replace an aging chlorine-treatment building with a new advanced 41,519-square-foot (12,655-square-metre) 400 mega litres-per-day plant is now in full progress at the Lakeview Water Treatment plant in Mississauga, Ontario.
In April, Quantum Murray Demolition began the demolition of the old facility, which consisted of 10 filters and a low-lift pumping station, to make way for the new 12-membrane facility which will use a combination of ozonation, ultrafiltration (UF) and ultraviolet (UV) technology.
“All three systems have been used for some time, but what is fairly new is the combination of all three,” says Peel water division manager Andrew Farr.
Kenaidan Contracting is the general contractor and CH2M Hill is the consultant on the project which is the largest component of the plant’s overall $209 million Phase Two expansion. Other work in this phase has included the construction of an administration building and a recently completed low-lift pumping station.
“We don’t have a lot of room here,” says Farr, in an explanation of why the combined ozone, UF, and UV technology is being used.
Not only does it provide faster treatment time, the combined system also requires less physical space. The footprint of the new plant will be only about 25 per cent of the space a conventional treatment plant would require. That will allow the region to preserve a considerable amount of adjacent greenspace and a baseball diamond.
The decommissioning and demolition of the old structure, parts of which dated back to the 1950s, won’t cause any disruption of loss of service, says Farr.
“We have capacity.”
The work currently underway is the culmination of a long-planned redevelopment designed to meet the water needs of Peel’s growing population. A Phase 1 expansion started in 2003 and, as part of that phase, an advanced treatment building was constructed in 2007.
Sandwiched between that one and the one to be built is a conventional chlorine treatment plant erected sometime in the 1960s. “But it is still a good functioning plant,” says Farr.
That middle section, however, will eventually be retrofitted and, by 2020, Lakeview will be a 100 per cent ozone, UF and UV treatment facility.
As for the current project, it is progressing fairly smoothly, says Kenaidan senior site superintendent Dave Ramberg.
With the exception of the foundation, all of the old treatment building has been knocked down by Quantum Murray crews.
Still, considerable dewatering will be required when excavation starts because the slab level is actually below the water level of Lake Ontario, he says.
With the building expected to consume 32,000 cubic metres of concrete, one of the biggest pieces of the project will be the formwork. It will be done by Kenaidan’s own crews in partnership with MJR Contractors. To match other buildings on the grounds, the cladding will be precast concrete.
Right now there are only about 30 workers on site, but Ramberg expects that will climb to approximately 120 when the project hits its peak in summer 2012. There will also be tower cranes — one on the north side of the site and a second one at the south side.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Widespread opposition to Ontario College of Trades membership classes
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- Ontario General Contractors Association launches letter writing campaign about College of Trades
- Aspen Ridge continues work on Scenic on Eglinton condos in Toronto
- Construction to start soon on Mission, British Columbia health centres
- Why re-tendering construction contracts after cancelling requests for proposals is fraught with risk
- Teamsters union aims to organizes Windsor Essex Parkway construction dump truck drivers
- Canada’s trade surplus in March increased but remained negligible
- Historic York House in Fredericton, New Brunswick sold to ADI Capital
- Painting and sand blasting firm fined $70,000 in connection with workplace injury in Hamilton, Ontario
- Nine nabbed in Quebec corruption bust
- Canada Lithium signs MOU with First Nations
- Almost fit for a King
- Contractors warned about PST transition
- Fort McMurray aggregate producer expands to meet demand
- Another multi-billion dollar LNG terminal proposed for Kitimat
- Best open shop contractors honoured
- Learning to dig safely in B.C.
- Review of Saskatchewan labour laws concerns unions
- Big deal for Ritchie Bros.
- Contracts awarded for 17 Wing in Winnipeg
- Highway 3 improvement contracts awarded
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More