September 30, 2011
FEATURE | Concrete/Masonry
Concrete pour underway at $160 million Mississauga, Ontario wastewater treatment plant
North America Construction is now in the midst of pouring 29,000 cubic metres of concrete for nine treatment tanks at Mississauga’s Clarkson Wastewater Treatment Plant
The concrete pour is part of an overall $160-million expansion that will increase the plant’s treatment capacity from 200 to 350 mega-litres a day. The pour started in April and will continue until July 2012.
While a massive undertaking, the preconstruction work and community relations initiatives have proved to be as equally challenging, suggest the project partners that include the contractor, owner Peel Region and its consultant, AECOM.
Located on Lakeshore Road within view of Lake Ontario, the plant has ample space for the expansion that is needed to meet rapid residential growth in Mississauga and Brampton, says William Fernandes, the region’s capital works manager for wastewater treatment.
Still, three long-defunct lagoons had to be decommissioned to make space for the tanks. “We couldn’t do this project without them (the lagoons) being removed.”
The approximately year-long removal operation carried out by another contractor consisted of dewatering — with the water retreated on site — and trucking the remaining solid waste to landfill sites, says Fernandes.
With the lagoons out of the way, excavation was able to proceed. That, however, proved to be particularly trying as large sections of the area is shale and in some spots the shale was six metres deep, says NAC project manager Mike Moylan.
“We excavated 200,000 cubic metres of earth, of which 150,000 cubic metres had to be trucked offsite.”
Ensuring mud and dirt from the trucks wouldn’t be deposited on Lakeshore Road and other area streets proved to be a challenge itself. A layer of coarse sand was applied at a separate dedicated entrance to the NAC work site.
“That didn’t work out very well. So we built a concrete pad,” says Moylan, explaining the truck tires are washed at the pad before exiting the site. Chemical dust suppressant is also sprayed on the internal roads.
A good measuring gauge on the success of those initiatives is the substantial decrease of area resident complaints about dust and dirt, says Fernandes.
Construction of the tanks is now in full progress and it involves pouring about 150 metres of concrete on a daily basis. The slabs for the tanks, which include primary and secondary aeration, and secondary final, are 450-mm-thick and the walls are between 350- and 450-mm-thick, says Moylan.
With an estimated 60 to 70 truckloads of concrete entering the plant weekly, a high degree of coordination between NAC and supplier St. Mary’s Cement is crucial, he says.
“Sometimes we schedule pours at 5:30 a.m. in the morning so their (St. Mary’s) trucks can beat the morning traffic rush. But that isn’t always possible and sometimes we have to cope with delays.”
AECOM has an on-site team of structural inspectors to ensure the concrete has the desired strength says Ignatius Ip, associate manager of wastewater engineering.
It also uses the services of material performance specialist, Davroc Consulting Engineers. The results of Davroc tests are posted on line about eight days after they are conducted, says Ip.
NAC will have an estimated workforce of 120 men on site when the project hits its peak later this fall, says Moylan, who estimates another 40 subcontractors will working there over the life of the project.
While the concrete pour will be finished next July, the project won’t be completed until June 2013. As the general contractor, NAC is also responsible for a massive amount of other work including equipment installation, mechanical/electrical connections and the construction of the blower building, says Moylan.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Widespread opposition to Ontario College of Trades membership classes
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 267 projects with a total value of $4,935,993,413 that Reed Construction Data Building Reports reported on Friday.
LIGHT RAIL TRANSIT EXPANSION, STATIONS
$2,200,000,000 Toronto ON Prebid
$47,902,962 Clarington ON Tenders
$40,000,000 North York ON Negotiated
| CURRENT STORIES |
- Infrastructure Ontario launches vendor of record process
- Dominus continues construction on 57-storey L Tower condos in Toronto
- Courts rule on low bid bypass and cancellation
- Monarch continues building Waterscapes on Toronto lakefront
- Nordenstrom new Canadian executive director for North American Insulation Manufacturers Association
- Windsor, Ontario lets commercial landowners keep Jersey barriers in place
- Canada’s trade surplus in March increased but remained negligible
- Milestone Environmental inks $7.3 million sediment capping project near Marathon, Ontario
- Romney will build TransCanada Keystone XL pipeline himself if he has to
- Ontario Municipal Board hearing scheduled for David Dunlap Observatory lands in Richmond Hill
- New West Residential project
- Contractors willing to share expertise about mill safety
- Changes to experience ratings draw cheers and jeers
- Lack of rental housing impacting Saskatchewan mega-project
- Rebuilding a Bridge
- Continuing education is vital for the industry
- Opposing campaigns launched over Bill-377
- Nine arrested in Montreal corruption probe
- Alberta worker crushed
- BC Place named the Stadium of the Year
- Bird secures $235 million in contracts
- NAIT Alumni honoured
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More