October 27, 2011
TOM ARBAN
A key reason for the Mohawk College project’s success was that the design/engineering team worked out the conceptual design together. A Building Information Modeling (BIM) design process was used and building costs were carefully tabulated early.
FEATURE | General and Trades Contracting
How Mohawk College in Hamilton fast-tracked construction
In an era when fast-track timelines are the norm for so many construction projects occasionally the pace of construction shifts into an even higher gear.
A 40,000 square-foot addition to Mohawk College in Hamilton is a case in point. Just one month after the architect was retained, the first tender package for excavation was issued and construction followed the next month.
Developer/builder Arcturus Realty Corporation had a foundation permit in its hands about eight weeks after concept design drawings commenced. That’s four to 10 months quicker than most projects of that size and scope, according to Ron Taylor, project manager of Arcturus.
Taylor adds that only 14 months after construction started, the new Learning Exchange and Cummings E-library was completed on target for a LEED Gold certification.
A key reason for the project’s success was that the design/engineering team worked out the conceptual design together. A BIM (Building Information Modeling) design process was used and building costs were carefully tabulated early, minimizing potential budget shortfalls that could lead to design changes during construction.
TOM ARBAN
One of the design objectives for Mohawk’s new addition was clear circulation routes throughout the campus.
The college administration played a role in keeping things rolling by making decisions on design and other aspects of the project quickly, Taylor points out.
As speedy as the design/construction pace was, however, students weren’t left out of the design.
“We had over 2,000 students participate in workshops, surveys online and blogs.”
Completed last year, the new learning centre is a model of efficiency, not just in energy savings but also in the square footage because 75 per cent of the building is dedicated to learning. That is 25 per cent higher than most educational institutes.
The efficiencies are partly because the design features few corridors but a lot of open space with study or “casual learning” areas, says Vaidila Banelis, partner in charge of design for the project’s architect Zeidler Partnership Architects.
Taylor adds the structure and systems of the building are exposed to create “a living lab” for students in architectural technology, building sciences and associated curriculums housed in the new addition. “Even the mechanical rooms are set up so teachers can take students in to examine the systems.”
One of the design objectives was to create clear circulation routes through a campus that had expanded in a hodge-podge manner since it was constructed in the 1960s. The Zeidler Partnership chose to reorganize flow patterns through the use of an “interior urban street,” explains Banelis.
Another priority for the architect was to boost the profile of the college’s appearance to the general public by creating a new high-profile on the busy Fennel St. A two-storey glazed façade with bold signage was selected. A polychromatic glazing system (composed of laminated color film) creates “a rainbow effect” of the color spectrum.
To create the “extremely energy-efficient” façade, the glazing is free of mullions, usually a weak thermal point in such facades.
Instead, Zeidler incorporated a series of stainless steel angles, bonded to the outside face of the glass, to support the glazing off a steel structure on the exterior of the building, says Banelis.
The view from the interior is through “a sheer piece of roughly 30-foot-high glazing.”
The unique design was originally developed by Zeidler for a project at Canary Wharf in London. “It has never been done in North America,” says the architect.
The glazing system was developed in conjunction with Contract Glaziers Inc. (CGI). Thermal imaging tests will determine the façade’s energy performance.
Banelis says the building requires about 50 per cent less energy than a comparable sized conventional building partly because of upgrades to the college’s heating plant. A dedicated outdoor air system consists of two sets of ductwork to separate the ventilation system from the conditioning system.
“With this system we don’t have to heat as much air,” says Banelis.
In addition to the new learning centre and library, the old library was recently converted into to the student services area designed to continue on the architect’s interior main street design theme.
Next on tap for Mohawk College’s renewal is a recreation centre which is scheduled to start next spring, says Taylor.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Widespread opposition to Ontario College of Trades membership classes
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 472 projects with a total value of $3,018,122,449 that Reed Construction Data Building Reports reported on Tuesday.
RESIDENTIAL, MIXED-USE, RECREATIONAL DEVELOPMENT
$514,000,000 Toronto ON Starts
$210,000,000 Toronto ON Prebid
CONDOMINIUM APARTMENT BUILDING
$138,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Infrastructure Ontario launches vendor of record process
- Dominus continues construction on 57-storey L Tower condos in Toronto
- Courts rule on low bid bypass and cancellation
- Monarch continues building Waterscapes on Toronto lakefront
- Nordenstrom new Canadian executive director for North American Insulation Manufacturers Association
- Windsor, Ontario lets commercial landowners keep Jersey barriers in place
- Milestone Environmental inks $7.3 million sediment capping project near Marathon, Ontario
- Romney will build TransCanada Keystone XL pipeline himself if he has to
- Ontario Municipal Board hearing scheduled for David Dunlap Observatory lands in Richmond Hill
- New West Residential project
- Contractors willing to share expertise about mill safety
- Changes to experience ratings draw cheers and jeers
- Lack of rental housing impacting Saskatchewan mega-project
- Rebuilding a Bridge
- Continuing education is vital for the industry
- Opposing campaigns launched over Bill-377
- Nine arrested in Montreal corruption probe
- Alberta worker crushed
- BC Place named the Stadium of the Year
- Bird secures $235 million in contracts
- NAIT Alumni honoured
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More