How British Columbia Supreme Court decided when low bidders sued over construction contracts
Bid Protest Bulletin | Paul Emanuelli
The legal defensibility of a low bid bypass decision will depend on the transparency of the factors relied on by the owner.
For example, in its decision in Tercon Contractors Ltd. v. British Columbia, the British Columbia Supreme Court held that preferences for factors other than price were acceptable as long as those preferences were disclosed in the tender call. The case involved a highway construction project on Vancouver Island. The low bidder, who proposed using steel to build the bridge, was bypassed in favour of a higher bid due to the Ministry of Transportation and Highway’s undisclosed preference for concrete. The low bidder sued, alleging that it should have been awarded the contract. The court agreed, finding that the concrete preference should have been disclosed.
The court found that if the Ministry preferred concrete even where that material was more expensive, then this preference “should have been quantified and the defendant ought to have informed all bidders that the concrete alternative would be preferred and by how much.”
Bid Protest Bulletin
Paul Emanuelli
The court found that the Ministry’s failure to disclose this evaluation factor amounted to the use of a hidden preference which “in effect incorporated an implied term with respect to its preference for concrete without giving notice to all bidders.” This undisclosed preference for concrete resulted in an unfair advantage to the winning bidder. The Ministry appealed but the decision was upheld by the British Columbia Court of Appeal. The plaintiff was ultimately awarded over $1 million in lost profit damages due to the Ministry’s hidden evaluation preference.
In contrast, in its decision in W.I.B. Co. Construction v. Central Okanagan School District No. 23, the British Columbia Supreme Court found that the owner was entitled to bypass the low bidder due to concerns with that bidder’s proposed site supervisor. The case involved a tender call for the construction of a school.
The court agreed that it is improper to disqualify a low bidder due to undisclosed criteria:
An owner may not arbitrarily or capriciously refuse to award Contract B to the lowest bidder since this would undermine the bidding system that has been developed over the years. It is quite improper for an owner to disqualify a bidder on criteria not disclosed in the Call for Tenders.
However, the court disagreed with the plaintiff’s assertion that the owner’s concerns over the proposed site supervisor constituted an improper hidden evaluation factor:
The defendants’ position is simply that the plaintiff’s proposed site supervision was so deficient that W.I.B. Co. was not a qualified bidder. The defendants go on to say that this decision was not made on the basis of some undisclosed term but rather from a concern about site supervision, which must have been evident to all bidders from the stipulation contained in the tendering documents that the name and resume of the proposed site superintendent had to be submitted with the bid.
Although the tender documents do not explicitly say so, it is reasonable to expect a bidder to recognize that the identity of the site superintendent would be an important factor in determining whether a bid was qualified.
This decision illustrates how an owner is entitled to depart from industry norms when making contract award decisions so long as it discloses the additional evaluation criteria it will rely on and applies those criteria in a fair and objective fashion. In the specific situation, the district’s request for information regarding the bidder’s proposed supervisor was found to be sufficient to negate any assertions of hidden criteria.
Paul Emanuelli’s procurement law practice focuses on all aspects of the tendering cycle including bid dispute resolution. This article is extracted from Emanuelli's Government Procurement textbook published by LexisNexis Butterworths.
Reach Paul at paul.emanuelli@procurementoffice.ca.
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- PCL Constructors works on Humber River Regional Hospital in Toronto
- Widespread opposition to Ontario College of Trades membership classes
- Disclosure bill an attack on unions, says organized labour
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 472 projects with a total value of $3,018,122,449 that Reed Construction Data Building Reports reported on Tuesday.
RESIDENTIAL, MIXED-USE, RECREATIONAL DEVELOPMENT
$514,000,000 Toronto ON Starts
$210,000,000 Toronto ON Prebid
CONDOMINIUM APARTMENT BUILDING
$138,000,000 Toronto ON Prebid
| CURRENT STORIES |
- Arthurs Review leaves unanswered questions
- Bluescape Construction works on 35-storey Market Wharf condos in Toronto
- How to renovate energy-guzzling tall buildings?
- Planned expansion to added 21,000-square-feet to ROCK Centre in Burlington, Ontario
- Carpenters’ Union apprentices compete in Kingston
- Bell and Urbacon receive facility design award
- New West Residential project
- Contractors willing to share expertise about mill safety
- Changes to experience ratings draw cheers and jeers
- Lack of rental housing impacting Saskatchewan mega-project
- Rebuilding a Bridge
- Continuing education is vital for the industry
- Opposing campaigns launched over Bill C-377
- Nine arrested in Montreal corruption probe
- Alberta worker crushed
- BC Place named the Stadium of the Year
- Bird secures $235 million in contracts
- NAIT Alumni honoured
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More