LATEST NEWS
Roadbuilding | Heavy Equipment | Steel | Concrete | Demolition | Professional Services
May 1, 2012
Detroit pier demolition begins after court rules
WINDSOR, ONT.
Work got underway almost immediately after a Michigan Court of Appeals ruling upheld the right of the Michigan Department of Transportation (MDOT) to complete the so-called $230 million Gateway Project for vehicles entering and exiting the United States at the Ambassador Bridge connecting Windsor and Detroit.
The court on April 13, upheld a lower court March ruling, and crews from Detroit-based Dan’s Excavating were on site the next day for 24 hours, staging equipment to begin the most controversial part of the work — demolishing a pier of a newly-built four-lane ramp.
The ramp had been built by the Ambassador Bridge to lead to a proposed new bridge to replace its current span opened in 1929. The company built ramps on both the Detroit and Windsor sides but they end abruptly. The company is still awaiting regulatory approval to construct the six-lane cable stayed bridge to which the ramps would connect.
But MDOT lawyers had argued that Pier 19 — the last pier holding up the ramp on the Detroit side — was constructed directly over a planned truck route that is part of Gateway, a mostly completed decade-long project that has reconfigured the Detroit side of the Ambassador Bridge to create more efficient links to freeways.
A few days after the ruling, crews were “about a third of the way done” with removing the beams between Piers 19 and 18, MDOT project manager Tia Klein said. A concrete pecker was used to demolish the deck and beams. The four, 60-foot pier columns and cap were then to be removed by crane.
Dan’s Excavating beat out Walter Toebe Construction, also of Detroit, for the job. Toebe had obtained the contract from the bridge company in a separate project to re-deck the bridge over the past year.
The court ordered owners of the privately-operated Ambassador Bridge to deposit $16 million in an account to pay for the work, with $9.4 million going to the design-build contractor and the rest for engineering, inspection and other fees.
Demolishing the pier is the first priority for MDOT because it desperately wants to open the long-delayed two-lane truck road by May 15 and improve the flow of commerce between the two countries. Currently trucks from Canada clearing U.S. Customs have to drive a convoluted route through city streets before they can enter freeways.
The demolished pier will allow trucks to seamlessly leave the Customs plaza and travel a third of a mile along bridge company property to a mostly finished ramp leading to Interstates 75 and 96. The road will be separated from passenger vehicles by concrete barriers.
Meanwhile work continues on the connecting truck ramp to fill in a 500-foot gap between two finished sections. One part is open air and the other merely piers and beams without decking for what’s known as Structure 32. Work on S-32 didn’t begin until the bridge company turned over to MDOT land upon which the structure is being built. This occurred after separate litigation in the years-long legal battles between the company and MDOT over completing Gateway. The company maintained it was living up to its share of construction work and blamed MDOT for making last-minute changes, delaying the project. The Michigan courts disagreed.
Klein said pier demolition should only take a week.
But completing the final few aspects of Gateway will take longer.
This includes a ramp leading from I-75 and I-96 to the Ambassador Bridge — and to Canada — for both cars and trucks. Currently drivers have to use service roads and city streets to enter the bridge.
“We’ll have everything inside the plaza completed and reopened to traffic by Sept. 30,” she said.
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 470 projects with a total value of $6,376,918,947 that Reed Construction Data Building Reports reported on Wednesday.
$104,727,250 Toronto ON Tenders
$50,000,000 Markham ON Tenders
$25,000,000 Toronto ON Prebid
| CURRENT STORIES |
- VIDEO: Economic Update May 21, 2013
- Prompt payment bill headed to committee
- Final Phase
- A return to core values a must for banks: Carney
- OHMPA on the road with informative seminars
- Local 675 strike ends after new agreement ratified
- NDP says it will support Liberal budget, averting spring election
- Measure of U.S. economy’s future health rises 0.6 per cent in April after March dip
- Terratec awarded Brighton, Ont. Lagoon Clean-Out Project contract
- Fundraising campaign to reach target for new Shriners Hospital for Children
- George Brown College building named after Tridel CEO
- Construction Site Arson
- VIDEO: Journal of Commerce Update for the week of May 27th, 2013
- Historic church renovation reaches new heights
- Hiring of foreign workers for hospital project outrages union
- Acetylene torch explosion causes significant damage
- Festival of Architecture hits Halifax
- Winnipeg Southwest Transitway wins award
- Vendor performance is key measurement
- NDP leader spoke to police about corruption
- Big contract down under for ATCO Structures
- RFQ issued for Kamloops hospital project
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More








