CONDOMINUM APARTMENTS, TOWNHOUSE & COMMERCIAL DEV Proj: 1311779-15
Scarborough, Metro Toronto Reg ON SUB AWARDS
Metro Gate Community, Solaris, Kennedy Rd & Hwy 401, M1M 1T3
$100,000,000 est
Start: March, 2009 Complete: January, 2011
Note: All trades are secured.
Project:concrete foundation, cast-in-place concrete structural frame, fuel fired heating system, proposed const of two condominium apartment buildings connected by a four storey podium. The Podium will have Green landscaped roofs. Phase Two, Ventus, a condominium apartment building proposed for the North East corner of the site can be followed under report number 9085385. Phase Three, 35,000 sq m of office space and retail space can be followed under report number 9068574. Owner is seeking LEED certification for this project.
Scope:603,000 square feet; 40 storeys; 2 storeys below grade; 2 structures; 968 units; parking for 500 cars; 16 acres
Development:New
Category:Religious bldgs; Retail, wholesale services; Commercial offices
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Excavating cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Foundation cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Formwork cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Reinforcing steel cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Concrete work cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Precast concrete cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural steel cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Masonry cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Glass, glazing cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Plumbing cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Warm air heating cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Air conditioning cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Ventilation cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Elevator cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Interior designer Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Jun 17, 2004. Last report Tue Mar 10, 2009.
This report Tue Mar 09, 2010.