HEAVY OIL UPGRADER Proj: 7158961-12
Wood Buffalo, Division No 16 AB DEFERRED
Long Lake Oil Sands Facility - Phase 2, Lease 27, near Gregoire Lake, 8 km SE of Hamlet of Anzac
$110,000,000 est
Note: This project has been put on hold. Design and construction schedules are undetermined. This project is previously known as the OPTI Long Lake Upgrader - Phase 2. Further update Spring 2011.
Project:03050; concrete materials, 05120; structural steel, 13120; metal building systems, 13200; storage tanks, 15120; piping specialties, 15220; liquid and gas storage tanks, 15780; energy storage tanks, proposed Upgrader will include a central processing facility consisting of steam generation, production processing, water treatment and recycling and cogeneration equipment; field facilities, including production pads and water source and disposal wells.
Scope:100,000 square feet; 1 storey; 2 structures
Development:Engineering
Category:Oil refineries; Pipelines; Misc industrial bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Jul 26, 2000. Last report Tue Dec 01, 2009.
This report Tue Mar 09, 2010.